SOS NERC PREP – RELIABILITY EXAM 2025 QUESTIONS AND ANSWERS

Puntuación
-
Vendido
-
Páginas
134
Grado
A+
Subido en
13-07-2025
Escrito en
2024/2025

A) Increase Net Interchange Schedule by 20 MWs. - ANS The Reliability Coordinator just informed you of a slow time error correction which will begin at the top of the next hour. Your EMS system will not let you change your scheduled frequency. Your Frequency Bias Setting is - 100 MW/.1Hz. What action should you take? A) Increase Net Interchange Schedule by 20 MWs. B) Inform the Reliability Coordinator that you cannot participate in the time error correction. C) Decrease Net Interchange Schedule by 20 MWs. D) Increase Net Interchange Schedule by 10 MWs. SOS NERC PREP – RELIABILITY EXAM 2025 QUESTIONS AND ANSWERS 2 Copyright ©2025 FYNDLAY ALL RIGHTS RESERVED. C) 1 & 4 - ANS A Balancing Authority has a sudden loss of a large block of load in its area. This loss will be seen instantaneously in the change of which of the following values? 1. Actual Net Interchange 2. Scheduled Frequency 3. Scheduled Net Interchange 4. Area Control Error A) 4 only B) 1 & 3 C) 1 & 4 D) 3 & 4 A) Tie lines readings - ANS Metered Data included in the calculation of ACE are: dynamic schedules, pseudo ties, actual frequency, and all __________. A) Tie lines readings B) Generators output 3 Copyright ©2025 FYNDLAY ALL RIGHTS RESERVED. C) Scheduled frequency indications D) Transformer load A) -100 - ANS Balancing Authority A is currently reading a system frequency of 60.00 Hz. Its Net Actual Interchange is +100 MW and its Net Scheduled Interchange is +200 MW. If Balancing Authority A's frequency bias setting is 100 MW/0.1 Hz, what is ACE? A) -100 B) 0 C) 10 D) 100 B) 25 MWs in - ANS A Balancing Authority has a Net Interchange Schedule of -250 MWs from 1200 to 1600 on a summer day. The Net Interchange Actual for those same hours respectively were -230 MW, -275 MW, -250 MW and -270 MW. What was the Balancing Authority's Inadvertent Interchange for the 4-hour period? A) 6 MWs out 4 Copyright ©2025 FYNDLAY ALL RIGHTS RESERVED. B) 25 MWs in C) 25 MWs out D) 6 MWs in D) Tie lines - ANS For the ACE equation to work properly, dynamic schedules, pseudo ties, frequency, and all ________________ must be metered. A) Generation B) Communications C) Transformers D) Tie lines B) The ACE will be a negative value and AGC will increase generation - ANS If the frequency bias setting is set to a less negative value than the frequency response of a Balancing Authority and a frequency increase is caused by a sudden loss of load in an external balancing area, what will be the result? A) The ACE will be zer

Mostrar más Leer menos
Institución
SOS NERC
Grado
SOS NERC











Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
SOS NERC
Grado
SOS NERC

Información del documento

Subido en
13 de julio de 2025
Número de páginas
134
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

SOS NERC PREP – RELIABILITY EXAM
2025 QUESTIONS AND ANSWERS




A) Increase Net Interchange Schedule by 20 MWs. - ANS The Reliability Coordinator just

informed you of a slow time error correction which will begin at the top of the next hour. Your

EMS system will not let you change your scheduled frequency. Your Frequency Bias Setting is -

100 MW/.1Hz. What action should you take?




A) Increase Net Interchange Schedule by 20 MWs.




B) Inform the Reliability Coordinator that you cannot participate in the time error correction.




C) Decrease Net Interchange Schedule by 20 MWs.




D) Increase Net Interchange Schedule by 10 MWs.




1 Copyright ©2025 FYNDLAY ALL RIGHTS RESERVED.

,C) 1 & 4 - ANS A Balancing Authority has a sudden loss of a large block of load in its area. This

loss will be seen instantaneously in the change of which of the following values?




1. Actual Net Interchange


2. Scheduled Frequency


3. Scheduled Net Interchange


4. Area Control Error




A) 4 only


B) 1 & 3


C) 1 & 4


D) 3 & 4




A) Tie lines readings - ANS Metered Data included in the calculation of ACE are: dynamic

schedules, pseudo ties, actual frequency, and all __________.




A) Tie lines readings


B) Generators output

2 Copyright ©2025 FYNDLAY ALL RIGHTS RESERVED.

,C) Scheduled frequency indications


D) Transformer load




A) -100 - ANS Balancing Authority A is currently reading a system frequency of 60.00 Hz. Its

Net Actual Interchange is +100 MW and its Net Scheduled Interchange is +200 MW. If Balancing

Authority A's frequency bias setting is 100 MW/0.1 Hz, what is ACE?




A) -100


B) 0


C) 10


D) 100




B) 25 MWs in - ANS A Balancing Authority has a Net Interchange Schedule of -250 MWs from

1200 to 1600 on a summer day. The Net Interchange Actual for those same hours respectively

were -230 MW, -275 MW, -250 MW and -270 MW. What was the Balancing Authority's

Inadvertent Interchange for the 4-hour period?




A) 6 MWs out



3 Copyright ©2025 FYNDLAY ALL RIGHTS RESERVED.

, B) 25 MWs in


C) 25 MWs out


D) 6 MWs in




D) Tie lines - ANS For the ACE equation to work properly, dynamic schedules, pseudo ties,

frequency, and all ________________ must be metered.




A) Generation


B) Communications


C) Transformers


D) Tie lines




B) The ACE will be a negative value and AGC will increase generation - ANS If the frequency

bias setting is set to a less negative value than the frequency response of a Balancing Authority

and a frequency increase is caused by a sudden loss of load in an external balancing area, what

will be the result?




A) The ACE will be zero and will take no AGC action


4 Copyright ©2025 FYNDLAY ALL RIGHTS RESERVED.
$14.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Fyndlay Kaplan University
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
357
Miembro desde
1 año
Número de seguidores
80
Documentos
18668
Última venta
4 días hace
Scholar\'s Sanctuary.

Explore a Vast Collection of Finely Made Learning Materials.

3.7

68 reseñas

5
32
4
8
3
13
2
6
1
9

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes