FDOT EXAM QUESTIONS AND ANSWERS
Which of these is a contract Document:
1. Standard Specifications
2. Basis of Estimates (BOE) Manual
3. Construction Project Administration Manual (CPAM) - Answer-1. Standard Specifications
Monthly payments are based on: - Answer-A Contractor's Monthly Estimate
Once the contract is executed, the only way to modify the contract document is through: -
Answer-1. Supplemental Agreements (SA)
2. Work Orders (WO)
3. Unilateral Payment
How are work order funds encumbered? - Answer-Through contingency Supplemental
Agreements (CSA)
When are unilateral payments used? - Answer-When the department and contractor cannot
agree on the terms or the contractor fails to timely execute: a work order or supplemental
agreement
What is the governing order of contract documents? - Answer-1. Special Provisions
2. Technical Special Provisions
3. Plans
4. Design Standards
5. Developmental Specifications
6. Supplemental Specifications
7. Standard specification
What are the resources used for Conventional Contracts? - Answer-1. Standard
Specifications
2. Basis of Estimates (BOE) Manual
3. Construction Project Administration Manual (CPAM)
Project Governance - Answer-Tier 1: Project Management Team: Functional Coordinators
and Vendor representatives. Chaired by Greg Patterson
Tier 2: Management Steering Team: Key Stakeholders and the Project Director. Chaired by
April Blackburn
Tier 3: Executive Steering Team: The Executive Project Sponsor
PMT - Answer-Project Management Team - Tier 1 of the project governance structure.
Chaired by Greg Patterson.
MST - Answer-Management Steering Team - Tier 2 of project governance. Key
Stakeholders and Project Director. Chaired by April Blackburn.
Which of these is a contract Document:
1. Standard Specifications
2. Basis of Estimates (BOE) Manual
3. Construction Project Administration Manual (CPAM) - Answer-1. Standard Specifications
Monthly payments are based on: - Answer-A Contractor's Monthly Estimate
Once the contract is executed, the only way to modify the contract document is through: -
Answer-1. Supplemental Agreements (SA)
2. Work Orders (WO)
3. Unilateral Payment
How are work order funds encumbered? - Answer-Through contingency Supplemental
Agreements (CSA)
When are unilateral payments used? - Answer-When the department and contractor cannot
agree on the terms or the contractor fails to timely execute: a work order or supplemental
agreement
What is the governing order of contract documents? - Answer-1. Special Provisions
2. Technical Special Provisions
3. Plans
4. Design Standards
5. Developmental Specifications
6. Supplemental Specifications
7. Standard specification
What are the resources used for Conventional Contracts? - Answer-1. Standard
Specifications
2. Basis of Estimates (BOE) Manual
3. Construction Project Administration Manual (CPAM)
Project Governance - Answer-Tier 1: Project Management Team: Functional Coordinators
and Vendor representatives. Chaired by Greg Patterson
Tier 2: Management Steering Team: Key Stakeholders and the Project Director. Chaired by
April Blackburn
Tier 3: Executive Steering Team: The Executive Project Sponsor
PMT - Answer-Project Management Team - Tier 1 of the project governance structure.
Chaired by Greg Patterson.
MST - Answer-Management Steering Team - Tier 2 of project governance. Key
Stakeholders and Project Director. Chaired by April Blackburn.