Network Diagram/Critical Path Questions
with Accurate Answers
backward pass correct answer To set construct the critical path using a
___________, you can start from the end date.
Concurrent Activities correct answer ____________ are sets of
activities can be done at the same time.
Crashing correct answer _________ is obtaining the greatest amount of
compression of the schedule/critical path for the least incremental cost
or time.
critical chain correct answer The ____________ builds on the critical
path method by going a step further by adding time buffers to account
for limited resources.
Fast-tracking correct answer ____________ is the process of executing
activities that were originally scheduled sequentially in parallel.
Finish-to-Finish Relationships (FF) correct answer ______________ is a
task relationship where the successor task cannot be completed until
the first task is completed. The second task will begin after some initial
progress on the first task has occurred. Both tasks will finish at the
same time.