(O+4M+P)/6 correct answer beta distribution Activity Duration=(O+4M+P)/6 (p-o)/6 correct answer What is the activity standard deviation formula? 1. traditional 2. extreme 3. agile correct answer name the project management method: 1. planning and sequential steps 2. focus on HR and is high stress 3. volatile and scope is likely to change, customer needs to remain in touch during project 5 4 correct answer Project process groups have ______ steps and project life cycle has ______ phases

Mostrar más Leer menos
Institución
Project Managememt
Grado
Project Managememt











Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
Project Managememt
Grado
Project Managememt

Información del documento

Subido en
2 de julio de 2025
Número de páginas
40
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

Project Management C722
Questions with Accurate Answers
(O+4M+P)/6 correct answer beta distribution
Activity Duration=(O+4M+P)/6


(p-o)/6 correct answer What is the activity standard deviation formula?


1. traditional
2. extreme
3. agile correct answer name the project management method:
1. planning and sequential steps
2. focus on HR and is high stress
3. volatile and scope is likely to change, customer needs to remain in
touch during project


5


4 correct answer Project process groups have ______ steps
and
project life cycle has ______ phases

,A decision point between phases of iteration. correct answer Which is
the definition of phase-gate?


activities and tasks correct answer Project deliverables are broken
down into ______________ and ________


activity estimates correct answer A project manager is creating a list of
anticipated project tasks while building a calendarized budget.


What is the key component of this budget called?


Adding functionality without considering impacts correct answer Which
is an example of project scope creep?




Adding functionality without considering impacts


Having an incomplete project scope


Continually using change management procedures


after action report correct answer What is another name for the
lessons learned review that is often used by the military and other
uniformed services?

,Agile correct answer _____________ project management is an
iterative approach to project management where the project team
works closely with the customer to deliver projects in usable chunks.


agile correct answer A potential challenge of using _______ project
management methods is that they depend heavily on the regular
availability and
decisiveness
of the customer.


alignment correct answer In project management the term
______________ is used to describe connecting project outcomes to
company goals.


apportion correct answer The ________________ method requires that
an overall project cost be provided based on the customer's budget or
similar projects. The overall budget is then allocated to the major work
areas required in the project (design, programming, testing,
documentation, user training).


as a series of functional parts correct answer How are project outcomes
delivered on a project using agile management methods?

, assumptions correct answer Project charters often include the project
scope, objectives, and


Axelos correct answer Which organization oversees the PRINCE2
certification?




AXELOS, Ltd


Association for Project Management (APM)


Project Management Institute (PMI)


International Project Management Association (IPMA)


baseline budget correct answer Project costs will be monitored by
comparing actual costs to the __________ __________


baseline correct answer The ______________ determines what is
included in the scope, what the schedule is, and what the costs are


beta distribution correct answer The _________ ______________ still
uses the three estimates (optimistic, most likely, and pessimistic) but
places emphasis on the most likely estimate.
$27.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
starwid Yale University
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
13
Miembro desde
6 meses
Número de seguidores
1
Documentos
8058
Última venta
4 días hace

3.3

4 reseñas

5
1
4
0
3
2
2
1
1
0

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes