100% de satisfacción garantizada Inmediatamente disponible después del pago Tanto en línea como en PDF No estas atado a nada 4.2 TrustPilot
logo-home
Examen

WGU - C722: Units 2 to 8 OA Styles Questions & Answers

Puntuación
-
Vendido
-
Páginas
17
Grado
A+
Subido en
02-07-2025
Escrito en
2024/2025

-Management chooses which areas to emphasize in the weighted model correct answer What is the major difference between a Non-Weighted and Weighted Factor Scoring Model? -Bias is removed from the survey in the weighted model -Costs are lower to run the final analysis in the non-weighted model -Management chooses which areas to emphasize in the weighted model -They are both comparable models, so no major difference between them -Move tasks around to more efficiently allocate project team members -Determine when new team members should be on-boarded correct answer Why does a project manager use a resource histogram in the planning stage? (Choose two:) -Move tasks around to more efficiently allocate project team members -Identify tasks with slack on the critical path -Analyze projected cost variances -Determine when new team members should be on-boarded

Mostrar más Leer menos
Institución
Project Managememt
Grado
Project Managememt










Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
Project Managememt
Grado
Project Managememt

Información del documento

Subido en
2 de julio de 2025
Número de páginas
17
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

WGU - C722: Units 2 to 8 OA
Styles Questions & Answers
-Management chooses which areas to emphasize in the weighted
model correct answer What is the major difference between a Non-
Weighted and Weighted Factor Scoring Model?


-Bias is removed from the survey in the weighted model
-Costs are lower to run the final analysis in the non-weighted model
-Management chooses which areas to emphasize in the weighted
model
-They are both comparable models, so no major difference between
them


-Move tasks around to more efficiently allocate project team members
-Determine when new team members should be on-boarded correct
answer Why does a project manager use a resource histogram in the
planning stage? (Choose two:)


-Move tasks around to more efficiently allocate project team members
-Identify tasks with slack on the critical path
-Analyze projected cost variances
-Determine when new team members should be on-boarded

,6 days correct answer The parks department is putting in new baseball
fields. The director asks for an estimate from the contractor for the
project length, in order to determine whether they will need to cancel
or postpone the upcoming baseball season. The contractor explains
that it all depends on the weather. Most months there are 5 days of
rain where they can't work. The least amount it has ever rained in the
last 10 years was 1 day. Weather forecasts show that there could be as
many as 12 days of significant rain. Using a triangular three-point
estimate, how many bad weather days will the baseball field project
need built into the schedule?


-4.5 days
-5 days
-5.5 days
-6 days


8 correct answer Over the summer, the facilities department of a
school district is going to repaint all the classrooms in the high school.
The director estimates that each classroom will take four hours to
paint. There are eighty classrooms in the building. How many weeks will
the painting take if only one painter is available for the project?


A business strategy correct answer Which of the following is made up
of the activities, methods, tactics, etc. that will be employed to meet
business goals?

, -A business strategy
-PMBOKs
-The project lifecycle
-Customer retention


About 10 weeks correct answer If a project manager calculates an SPI of
1.2 for a project that was originally planned to take 3 months, how long
is it probably going to take now?


The Schedule Performance Index (SPI)
SPI = EV/PV
SPI values greater than 1 mean that the project team is completing
more work in less time than expected. This is a good result. If SPI is less
than 1, which indicates that the project team is accomplishing less work
for the time allowed.


-About 10 weeks
-Nothing changed - still 3 months
-Almost 4 months
-More information is needed


Ad hoc correct answer Which of the following is the lowest level of
project management maturity for an organization?
$16.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
starwid Yale University
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
13
Miembro desde
6 meses
Número de seguidores
1
Documentos
8058
Última venta
4 días hace

3.3

4 reseñas

5
1
4
0
3
2
2
1
1
0

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes