Terms in this set (25)
To ensure the success of B. The order specified by the business
our project, in what order representatives
should we execute the
work, taking into account Explanation
the necessary It is largely the business representatives who outline
dependencies and risk the priority of the functional requirements on the
mitigation tasks? project. That prioritization is then a key driver for the
A. The order specified by order in which we execute the work. Domain: Value-
the project manager Driven Delivery Source: PMI-ACP Exam Prep Page:
B. The order specified by 101
the business
representatives
C. The order specified by
the project team
D. The order specified by
the project management
office (PMO)
, A. Whether they are building the right product
When your team presents
a product demonstration,
Explanation
what do they expect to
Product demonstrations give the team feedback
learn?
about whether they are building the right product so
A. Whether they are
far. They typically don't provide feedback about user
building the right product
story estimates or QA testing results. Although the
B. How accurate their
customer and the team may discuss the features to
user story estimates were
be worked on next as part of the review meeting, the
C. Whether the increment
demo itself is simply an opportunity to get feedback
passes QA testing
about the increment they have just finished. Domain:
D. How the customer
Value-Driven Delivery Source: PMI-ACP Exam Prep
wants them to proceed
Page: 129
, A small business is C. Calculate the NPV of both projects, and select the
considering two potential one with the higher value.
projects and is wondering
which one to implement Explanation
first. Project A returns To weigh the value of two projects, we would
$700,000 in 5 years, and calculate the NPV of both projects (to determine
Project B returns their value in today�۪s terms), and select the one that
$400,000 in 2 years. What has the higher value. Domain: Value-Driven Delivery
should the organization Source: PMI-ACP Exam Prep Page: 89
do?
A. Calculate the NPV of
both projects, and select
the one with the lower
cost.
B. Calculate the IRR of
both projects, and select
the one with the lower
rate.
C. Calculate the NPV of
both projects, and select
the one with the higher
value.
D. Calculate the ROI of
both projects, and select
the one with the longer
payback period.