CLC 222 Module 3 Exam Contract
Management Questions and Answers
(Verified Answers)
What is a Contracting Officer Representative? - CORRECT
ANSWER>>A technical representative that is appointed by the
contracting officer through a designation letter
The procuring Contracting Officer, Administrative Contracting Officer,
Termination Contracting Officer, and the Contracting Officer's
Representative are key players in the acquisition process. From the
following statements, choose the CORRECT ANSWER: - CORRECT
ANSWER>>The contracting officer appoints the contracting officer's
representative in writing
In your position as a COR, Conflict of Interest rules and regulations
prohibit you from: - CORRECT ANSWER>>Working on a government
matter that has an effect on your personal financial interests
The contractor gives a federal employee tickets to a local production of
a Broadway play. The tickets are worth $20. Was an ethics law or
regulation violated? If so, which one? - CORRECT ANSWER>>No
ethics law or regulation has been violated; however the appearance of
impropriety might exist
When writing a SOW use the SMART principle which stands for: -
CORRECT ANSWER>>Specific, Measurable, Accountable,
Reasonable, Time-Based
, All of the following are elements of a Purchase Request
EXCEPT________. - CORRECT ANSWER>>COR nomination letter
The purpose of evaluation factors is to represent the key areas of
importance and emphasis to be considered in the source selection
decision. Of the statements below, the only true statement is: -
CORRECT ANSWER>>The offeror can be evaluated against the
evaluation factors and compared to other offerors' proposals
What are the differences between contracting by negotiation and
sealed bidding? - CORRECT ANSWER>>Negotiation allow for
communication and evaluation factor tradeoffs with the contractor
Elements of a Market Research report include: (Select all that apply) -
CORRECT ANSWER>>1. Product or service characterized
2. Available sources
3. Pricing
What is an Independent Government Estimate (IGE)? - CORRECT
ANSWER>>An independent detailed assessment developed by a
government team member...
A Statement Of Work should include the following: - CORRECT
ANSWER>>The work to be performed, location of work, period of
performance, deliverable schedule, any special requirements
Acquisition Planning's principal purpose is to ensure that the
government meets its needs in the most effective, economical and
Management Questions and Answers
(Verified Answers)
What is a Contracting Officer Representative? - CORRECT
ANSWER>>A technical representative that is appointed by the
contracting officer through a designation letter
The procuring Contracting Officer, Administrative Contracting Officer,
Termination Contracting Officer, and the Contracting Officer's
Representative are key players in the acquisition process. From the
following statements, choose the CORRECT ANSWER: - CORRECT
ANSWER>>The contracting officer appoints the contracting officer's
representative in writing
In your position as a COR, Conflict of Interest rules and regulations
prohibit you from: - CORRECT ANSWER>>Working on a government
matter that has an effect on your personal financial interests
The contractor gives a federal employee tickets to a local production of
a Broadway play. The tickets are worth $20. Was an ethics law or
regulation violated? If so, which one? - CORRECT ANSWER>>No
ethics law or regulation has been violated; however the appearance of
impropriety might exist
When writing a SOW use the SMART principle which stands for: -
CORRECT ANSWER>>Specific, Measurable, Accountable,
Reasonable, Time-Based
, All of the following are elements of a Purchase Request
EXCEPT________. - CORRECT ANSWER>>COR nomination letter
The purpose of evaluation factors is to represent the key areas of
importance and emphasis to be considered in the source selection
decision. Of the statements below, the only true statement is: -
CORRECT ANSWER>>The offeror can be evaluated against the
evaluation factors and compared to other offerors' proposals
What are the differences between contracting by negotiation and
sealed bidding? - CORRECT ANSWER>>Negotiation allow for
communication and evaluation factor tradeoffs with the contractor
Elements of a Market Research report include: (Select all that apply) -
CORRECT ANSWER>>1. Product or service characterized
2. Available sources
3. Pricing
What is an Independent Government Estimate (IGE)? - CORRECT
ANSWER>>An independent detailed assessment developed by a
government team member...
A Statement Of Work should include the following: - CORRECT
ANSWER>>The work to be performed, location of work, period of
performance, deliverable schedule, any special requirements
Acquisition Planning's principal purpose is to ensure that the
government meets its needs in the most effective, economical and