Summary Critical Path Analysis

Puntuación
-
Vendido
-
Páginas
2
Subido en
28-09-2020
Escrito en
2019/2020

Describes what a critical path analysis is, what a manager needs to know to use the technique, features of a critical path, key points of a critical path, and the advantages and disadvantages of it.

Institución
Grado








Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Nivel de Estudio
Editores
Tema
Curso

Información del documento

Subido en
28 de septiembre de 2020
Número de páginas
2
Escrito en
2019/2020
Tipo
Resumen

Temas

Vista previa del contenido

Theme 3 Topic 9
Critical Path Analysis
Critical Path Analysis
Critical Path Analysis – using a network diagram to show
the tasks taken to complete a project in the minimum time
possible

 Shows the sequence of activities required for the
project and the order in which they can be
completed
 Its purpose is to plan projects in a way which
enables a project to be completed in the shortest
time possible

To Use the Technique a Manager Needs to Know:

 What different tasks are involved
 The length of time each task is expected to take
 The order the tasks must be completed in – some can’t be started until another has finished

Features of a Critical Path Analysis:

Feature Explanation
Nodes and Node  The circles represent a point in time at the start or end of an activity
Numbers  Nodes are split into three
 The left half of the node contains the number of the node – provides a unique
identity for each node
Earliest Start  The right half of the node is split in two
Time (EST)  The top segment shows the EST that an activity can commence
 Depends on the completion of the previous activity
 For the starting activity, the EST is always zero
Latest Finishing  The bottom segment shows the LFT
Time (LFT)  The latest time an activity can finish without delaying the overall project
Arrows  Represent production activities, they must go left to right and begin and end
with a node
 Below the line – a number which represents the length of time it takes to
complete that activity
 Above the line – a letter or description of the activity that the line represents
The Critical Path  Critical Path – the sequence of activities in a project that must be completed
within a designated time in order to prevent any delay in overall completion of
the project
 Is shown by the symbol // over the arrow
Total Float  Total Float – the amount of time that an activity can be delayed by without
delaying the entire project
 Total Float for an Activity = LFT – Duration of Activity – EST

Key Points of a Critical Path Analysis:

 Must start and end on a single node
 No lines should cross each other
 There is no limit on the number of activities that link to a single node
 When drawing an activity, do not add the end node until you have looked to see which activity follows
 It is helpful to draw networks with large circles and short lines – able to write figures in the nodes

Advantages of Critical Path Analysis Disadvantages of Critical Path Analysis
$4.81
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada


Documento también disponible en un lote

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
emily1744 Greenhead College
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
42
Miembro desde
5 año
Número de seguidores
23
Documentos
168
Última venta
8 meses hace

4.3

15 reseñas

5
11
4
1
3
1
2
1
1
1

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes