SAFe APM Exam Prep COMPLETE EXAM QUESTIONS AND ACCURAT
SAFe APM Exam Prep
ANSWERS |ALREADY PASSED!!
Study online at https://quizlet.com/_g45u8y
1. What determines when a Feature is ready to move to Policies
the next column in the Program Kanban?
Policies
Work in process (WIP) limits
Definition of done
Definition of ready
2. Which two sources are most likely to help when creat- Agile Teams
ing a compelling product Vision? (Choose two.) Customer feedback
Agile Teams
Customer feedback
Competitor analysis
Stakeholder analysis
Team Backlogs
3. Which aspect of whole-product thinking captures a Augmented product
Customer's price sensitivity?
Augmented product
Expected product
Potential product
Generic product
4. To foster alignment during the PI execution, the Prod- PO sync
uct Manager may often be asked to facilitate which
event in the closed loop system?
PO sync
Scrum of Scrums
System Demo
Inspect & Adapt
5. What are the key elements of the Solution Intent? Specifications, designs,
Specifications, designs, and tests and tests
, SAFe APM Exam Prep
Study online at https://quizlet.com/_g45u8y
Strategic Themes and nonfunctional requirements
Epics, Features, and Stories
Customer segments and product Vision
6. Which horizon describes the desired state as stable Horizon 1
solutions that deliver high value with minimal new
investment?
Horizon 1
Horizon 0
Horizon 2
Horizon 3
7. What are two outputs of a PI Planning event? (Choose Committed PI Objectives
two.) Program Board with De-
Top 10 Features pendencies
PI retrospective action items
Committed PI Objectives
Program Board with Dependencies
10-15% allocation to the Architectural Runway
8. What does the Solution Context describe? The environment in which
The behavior of the Solution the Solution operates
The type of Solution the Customer will use
The environment in which the Solution operates
The Customer segment for the Solution
9. Who are the three main stakeholders involved in cal- Release Train Engineer
culating a Feature's weighted shortest job first values?
(Choose three.)
Release Train Engineer
Product Manager
System Architects
Scrum Master
, SAFe APM Exam Prep
Study online at https://quizlet.com/_g45u8y
System Team
Business Owners
10. Which ceremony tracks the ART's progress towards ART sync
meeting the Program Increment objectives?
ART sync
Participatory budgeting
Portfolio minimum viable product reviews
Weighted shortest job first prioritization
11. Under what circumstance would a team create a Story When stories work togeth-
map? er to support a workflow
When stories for a single Feature spans multiple
teams
When stories are dependent on one another
When stories impact more than one Customer per-
sona
When stories work together to support a workflow
12. Which three sources can Product Managers leverage Strategic Themes
for innovation ideas? (Choose three.) Agile Teams
Code reviews Suppliers
Strategic Themes
DevOps
Agile Teams
The Lean-Agile Center of Excellence
Suppliers
13. What happens when an Epic benefit hypothesis is Stop working on the Epic;
proven false? a new Epic and hypothesis
The Epic is discarded and no more work will be done must be created and ap-
on that initiative proved for work to contin-
Stop working on the Epic; a new Epic and hypothesis ue
SAFe APM Exam Prep
ANSWERS |ALREADY PASSED!!
Study online at https://quizlet.com/_g45u8y
1. What determines when a Feature is ready to move to Policies
the next column in the Program Kanban?
Policies
Work in process (WIP) limits
Definition of done
Definition of ready
2. Which two sources are most likely to help when creat- Agile Teams
ing a compelling product Vision? (Choose two.) Customer feedback
Agile Teams
Customer feedback
Competitor analysis
Stakeholder analysis
Team Backlogs
3. Which aspect of whole-product thinking captures a Augmented product
Customer's price sensitivity?
Augmented product
Expected product
Potential product
Generic product
4. To foster alignment during the PI execution, the Prod- PO sync
uct Manager may often be asked to facilitate which
event in the closed loop system?
PO sync
Scrum of Scrums
System Demo
Inspect & Adapt
5. What are the key elements of the Solution Intent? Specifications, designs,
Specifications, designs, and tests and tests
, SAFe APM Exam Prep
Study online at https://quizlet.com/_g45u8y
Strategic Themes and nonfunctional requirements
Epics, Features, and Stories
Customer segments and product Vision
6. Which horizon describes the desired state as stable Horizon 1
solutions that deliver high value with minimal new
investment?
Horizon 1
Horizon 0
Horizon 2
Horizon 3
7. What are two outputs of a PI Planning event? (Choose Committed PI Objectives
two.) Program Board with De-
Top 10 Features pendencies
PI retrospective action items
Committed PI Objectives
Program Board with Dependencies
10-15% allocation to the Architectural Runway
8. What does the Solution Context describe? The environment in which
The behavior of the Solution the Solution operates
The type of Solution the Customer will use
The environment in which the Solution operates
The Customer segment for the Solution
9. Who are the three main stakeholders involved in cal- Release Train Engineer
culating a Feature's weighted shortest job first values?
(Choose three.)
Release Train Engineer
Product Manager
System Architects
Scrum Master
, SAFe APM Exam Prep
Study online at https://quizlet.com/_g45u8y
System Team
Business Owners
10. Which ceremony tracks the ART's progress towards ART sync
meeting the Program Increment objectives?
ART sync
Participatory budgeting
Portfolio minimum viable product reviews
Weighted shortest job first prioritization
11. Under what circumstance would a team create a Story When stories work togeth-
map? er to support a workflow
When stories for a single Feature spans multiple
teams
When stories are dependent on one another
When stories impact more than one Customer per-
sona
When stories work together to support a workflow
12. Which three sources can Product Managers leverage Strategic Themes
for innovation ideas? (Choose three.) Agile Teams
Code reviews Suppliers
Strategic Themes
DevOps
Agile Teams
The Lean-Agile Center of Excellence
Suppliers
13. What happens when an Epic benefit hypothesis is Stop working on the Epic;
proven false? a new Epic and hypothesis
The Epic is discarded and no more work will be done must be created and ap-
on that initiative proved for work to contin-
Stop working on the Epic; a new Epic and hypothesis ue