Construction Project Administration Exam Questions And Answers 100% Pass What is the best skill essential to a project managers success that will result in a "best solution" outcome? - ANS Problem Solving Cost control involves the use of "comparisons" to indicate the need to do what? - ANS Change methods, change techniques, or change crew composition to earn profit What are the 5 phases of the construction process? - ANS Predesign, Design, Bid/Award, Construction, Post Construction Which of the following is a fundamental element of a contract? A. Time extension B. Revised Scope of work C. Mutual acceptance D. Exchange of money - ANS B. Revised Scope of Work Which of the following contract types have the most risk for the contractor? A. Lump Sum B. Unit Price C. Cost plus D. Cost plus GMP - ANS A. Lump Sum ©EVERLY 2025 ALL RIGHTS RESERVED Which of the following contract types are best used if the scope is defined but not the quantities of material? A. Unit Price B. Lump Sum C. Cost Plus D. Cost Plus GMP - ANS A. Unit Price What is the advantage of forming a corporation? A. Value of corporation can't go down from initial purchase price B. Reduced personal liability of shareholders C. Less taxes paid than limited liability corporation D. Quick decision making especially for large companies - ANS B. Reduced personal liability of shareholders In the construction industry, which legal entity is often a temporary arrangement? A. Partnership B. Sole proprietorship C. Limited liability corporation D. Joint ventures - ANS D. Joint ventures True/False: The traditional project delivery system, also frequently referred to as "design-bid- build" has been the most used project delivery system since the late 1800s - ANS True True/False: In the traditional project delivery system, the contractor is responsible for providing the labor, material, equipment, and construction documents, based on the owner's needs. - ANS False ©EVERLY 2025 ALL RIGHTS RESERVED True/False: In the traditional project delivery system, the capital projects officer is concerned primarily with the disbursement of funds for the project. - ANS False True/False: In the CM delivery system, the design manager is responsible for the coordination of shop drawings, submittals, layout, subcontractor organization, payment verification, and whatever duties are assigned by the construction superintendent or construction administrator. - ANS False True/False: The Engineering-Procurement-Construction (E-P-C) system is a common delivery system for light construction facilities. - ANS False True/False: CM-at-Risk is similar to the GMP arrangement in the traditional system, except that the construction manager is involved in the conception and design of he project rather than entering after the completion of the contract documents. - ANS True True/False: In an Agency CM contracting arrangement, the construction manager does not have design or construction responsibilities. - ANS True True/False: In the Agency CM delivery system, the architect has a contract with the CM, but all prime contractors have contracts only with the Owner. - ANS False True/False: Some design-build firms contract out both the architectural and construction services components of a project. - ANS True True/False: One design-build delivery system is a hybrid of the others where a design and contracting firm form a joint venture/partnership for one specific project. The venture/partnership is usually dissolved when the project is complete. - ANS True The traditional contract project delivery system has three primary contractual parties: the owner, the architect, and t

Mostrar más Leer menos
Institución
Construction Project Administration
Grado
Construction Project Administration











Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
Construction Project Administration
Grado
Construction Project Administration

Información del documento

Subido en
15 de mayo de 2025
Número de páginas
39
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

©EVERLY 2025 ALL RIGHTS RESERVED




Construction Project Administration Exam
Questions And Answers 100% Pass



What is the best skill essential to a project managers success that will result in a "best solution"
outcome? - ANS Problem Solving


Cost control involves the use of "comparisons" to indicate the need to do what? -
ANS Change methods, change techniques, or change crew composition to earn profit



What are the 5 phases of the construction process? - ANS Predesign, Design, Bid/Award,
Construction, Post Construction


Which of the following is a fundamental element of a contract?
A. Time extension
B. Revised Scope of work
C. Mutual acceptance

D. Exchange of money - ANS B. Revised Scope of Work


Which of the following contract types have the most risk for the contractor?
A. Lump Sum
B. Unit Price
C. Cost plus

D. Cost plus GMP - ANS A. Lump Sum

, ©EVERLY 2025 ALL RIGHTS RESERVED




Which of the following contract types are best used if the scope is defined but not the
quantities of material?
A. Unit Price
B. Lump Sum
C. Cost Plus

D. Cost Plus GMP - ANS A. Unit Price


What is the advantage of forming a corporation?
A. Value of corporation can't go down from initial purchase price
B. Reduced personal liability of shareholders
C. Less taxes paid than limited liability corporation

D. Quick decision making especially for large companies - ANS B. Reduced personal liability of
shareholders


In the construction industry, which legal entity is often a temporary arrangement?
A. Partnership
B. Sole proprietorship
C. Limited liability corporation

D. Joint ventures - ANS D. Joint ventures


True/False: The traditional project delivery system, also frequently referred to as "design-bid-
build" has been the most used project delivery system since the late 1800s - ANS True


True/False: In the traditional project delivery system, the contractor is responsible for providing
the labor, material, equipment, and construction documents, based on the owner's needs. -
ANS False

, ©EVERLY 2025 ALL RIGHTS RESERVED


True/False: In the traditional project delivery system, the capital projects officer is concerned
primarily with the disbursement of funds for the project. - ANS False


True/False: In the CM delivery system, the design manager is responsible for the coordination
of shop drawings, submittals, layout, subcontractor organization, payment verification, and
whatever duties are assigned by the construction superintendent or construction administrator.
- ANS False


True/False: The Engineering-Procurement-Construction (E-P-C) system is a common delivery
system for light construction facilities. - ANS False


True/False: CM-at-Risk is similar to the GMP arrangement in the traditional system, except that
the construction manager is involved in the conception and design of he project rather than
entering after the completion of the contract documents. - ANS True


True/False: In an Agency CM contracting arrangement, the construction manager does not have
design or construction responsibilities. - ANS True


True/False: In the Agency CM delivery system, the architect has a contract with the CM, but all
prime contractors have contracts only with the Owner. - ANS False


True/False: Some design-build firms contract out both the architectural and construction
services components of a project. - ANS True


True/False: One design-build delivery system is a hybrid of the others where a design and
contracting firm form a joint venture/partnership for one specific project. The
venture/partnership is usually dissolved when the project is complete. - ANS True


The traditional contract project delivery system has three primary contractual parties: the
owner, the architect, and the ______________. - ANS Contractor

, ©EVERLY 2025 ALL RIGHTS RESERVED


The _________________ is an upper-management-level individual who is the ultimate decision
maker for the design firm on the project. - ANS Principal-in-charge


Hourly employees who are trained to perform specific tasks are called ____________. -
ANS Craftspeople


The owner's daily representative during the construction project is called
____________________. - ANS The owners project manager


Currently, the most common competitive bidding method for compensating the contractor,
while still allowing for changes to the scope of work during the construction period is called...
A. Lump-sum contract
B. Unit-price contract
C. Cost plus, with a guaranteed maximum price

D. Cost, plus a fee - ANS A. Lump-sum contract


The construction project delivery system provides a matrix of organization, with formal and
informal _______________ relationships between participants. - ANS Contractural


In building construction, much of the work is accomplished by _________________ who have
an agreement with the contractor to complete a specific portion of the work covered by the
contractor's contract requirements. - ANS Specialty Subcontractors


In the traditional delivery system, subcontractors should not communicate directly with the
architect but should approach the contractor's project manager or
________________________. - ANS Superintendent


The CM delivery system that has the several prime contractors contracting directly and
separately with the Owner and the construction manager in an advisory rule only providing
construction administration for the owner is called a ______________________. -
ANS Multiple Prime Contracting Arrangement
$13.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Everly Teachme2-tutor
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
18
Miembro desde
1 año
Número de seguidores
1
Documentos
2796
Última venta
2 meses hace
Study packs.

Find Quality Exam Materials made by professionals With A guaranteed A+

4.3

4 reseñas

5
2
4
1
3
1
2
0
1
0

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes