INSPECTOR EXAM
ANSWER ALL QUESTIONS IN THIS SECTION
QUESTION 1
what term basically means a plea deal for stormwater offenders? - ANSWERS-
consent order, which replaces penalties with fines.
QUESTION 2
how long does VSMP authority have to review SWM plan? - ANSWERS-15 days
to review and determine approval, and notify applicant.
QUESTION 3
How often must a VSMP authority inspect an LDA? - ANSWERS-Periodically.
QUESTION 4
all SWPPP requirements may be met by - ANSWERS-incorporating other plans
into reference, or by developing missing elements.
END OF
PAGE
1
, VA DEQ SWM LATEST
INSPECTOR EXAM
QUESTION 5
What must the DEQ issue to an operator before an LDA? - ANSWERS-a
construction GP
QUESTION 6
How soon after final grade of a site must vegetation be put in place? - ANSWERS-
within 7 days.
QUESTION 7
How long must operator keep routine inspection reports? - ANSWERS-At least 3
years after the GP expires/terminates.
QUESTION 8
How long does operator have to revise SWPPP if authority deems it necessary?
How long does local authority have to review any modifications to SWPPP? -
ANSWERS-7 days for operator to make changes, 60 days for authority to review
changes.
END OF
PAGE
2