Which of the following control parameters determines the scope of the MRP run in SAP S/4HANA?
- Processing key
- Purchase requisition
- Planned order
- Planning mode
- Schedule line ANS - Processing key
What is the highest organizational unit in warehouse management?
- Warehouse number
- Storage selection
- Storage bin
- Storage type ANS - Warehouse number
What happens when we post payment to a vendor? (choose 2)
- Clears vendor open items
- Creates material document
- Creates CO document
Increases on-hand inventory
- Creates accounting document
- Creates open item for vendor ANS - Clears vendor open items
- Creates accounting document
Which of the following in the manufacturing process can be automated? (choose 2)
- Order creation
,- Order release
- Material staging
- Material withdrawal posting
- Order archiving ANS - Order release
- Material withdrawal posting
Which of the following is NOT part of the standard SAP procurement process?
- Supply source determination
- Goods issue
- Invoice verification
- Purchase order monitoring ANS - Goods issue
Select all HCM organizational objects: (choose 4)
- Payroll area
- Org unit
- Persons
- Employee self-service
- Job
- Position
- Compensation ANS - Org unit
- Persons
- Job
- Position
What is true of S/4HANA? (choose 4)
- Multicore processors
- Can run on any database platform
,- Row based data model
- Big memory
- Mandatory to use the material ledger
- Business users must use Fiori ANS - Multi processors
- Big memory
- Mandatory to use the material ledger
- Business users must use Fiori
In SAP S4/HANA, the SOP (Sales Operations Planning) is being replaced with which process?
- COPA planning (COPA)
- Production Planning (PP)
- Integrated Business Planning (IBP)
- Material Requirements Planning (MRP) ANS - Integrated Business Planning (IBP)
What process in EWM is used for determining the best storage bin for a material?
- Picking
- Stock transfer
- Slotting
- Goods receipt ANS - Slotting
The employee master data is stored on objects called:
- Personnel file
- InfoType
- Personnel action
- Positions ANS - InfoType
List the first four procure to pay steps in the correct order:
, - Create the PO, Determine Requirements, Determine source of supply, Select the vendor
- Determine requirements, Select the vendor, Determine source of supply, Create the PO
- Determine Requirements, Determine source of supply, Select the vendor, Create the PO
- Determine source of supply, Determine Requirements, Select the vendor, Create the PO ANS - Determine
Requirements, Determine source of supply, Select the vendor, Create the PO
What is the hierarchy of major project steps?
- Activities
- Tasks
- Project plan
- WBS
- Network ANS - WBS
What is an output of MRP? (choose 2)
- Purchase order
- Sales order
- Planned order
- Purchase requisition
- Quotation ANS - Planned order
- Purchase requisition
A profit center cannot be assigned to which of the following?
- Asset
- Material
- Cost Center
- G/L Account ANS - G/L Account