CONSTRUCTION EXAM WITH CORRECT
QUESTIONS AND ANSWERS 2025
A notice of termination can be filed when? - RIGHT ANSWER -All construction activity, inside and
outside of the building is complete. Permanent stabilization has been verified.
A SWPPP site map will show all of the following? - RIGHT ANSWER -Location of BMP's, Phasing &
Sequence, Limits of Disturbance
Common types of erosion include? - RIGHT ANSWER -Gully, Sheet, and Rill
Discharge From Contaminated Ground Water - RIGHT ANSWER -Never an allowable discharge
from a construction site
NPDES - RIGHT ANSWER -Requirements for managing storm water activity on a construction site
are outlined in the following regulation
NPDES (National Pollutant Discharge Elimination System) - RIGHT ANSWER -Requirements for
managing storm water activity on a construction site are outlined in the following regulation?
Potential pollutant sources stored on a construction site may include? - RIGHT ANSWER
-Petroleum storage tanks, fertilizer, lime, and masonry materials.
Proper spill management should include all of the following? - RIGHT ANSWER -Fully stocked,
proper location, signage, and labeling.
Runoff controls include? - RIGHT ANSWER -Diversions, check dams, slope drains