by Experts
Why are systems for administrative, financial and contract closure critical during the end of
project transition phase? These systems help reduce the risk of disputes with suppliers,
employers and donors
Which statement best describes a project ectension scenario? The project team has
negotiated with the project donor to add time to the project calendar in order to finish the project.
Which of the following scope management activities is conducted during the end of the project
transition phase? Verify scope
What is an important characteristic of the end of project learning review process? It is
completed quickly