When submiting a change order keep the ________ and provide ______ to the customer
Original, Copies
Acceptance Plan Outlines the tasks, tools, staff, and skills necessary to test and document
the successful completion of a project.
Contents of Acceptance Plan • Date and time of test.
• Testing technicians.
• Testing witnesses.
• Equipment used:
- Make and model.
- Serial number.
- Equipment calibration dates.
• Test documentation.
• Date submitted.
• Date approved.
Test Documentation May be required between cabling install team and manufacturer
warranty
,Testing requirements should be discussed with owner or contractor when? before work
begins
Where do you submit Test Equipment Calibration Reports to? Included in test document
Punch List Log Contents • Walk-through punch list.
• Participants.
• Time and date.
• Record of completion.
• Client acceptance.
As Built Drawing Contents Pathways
Cable
Telecommunication Spaces
Work Area Outlets
_______ _______ _______A detailed, time sensitive study of the volume of flow of information
(voice, data, video) over a network system. This document will allow the client to assess
network bandwidth usage. Network Traffic Studies
Warranty and License Documentation • An installation warranty.
,• Vendor/manufacturer performance warranty.
- Extended equipment warranty.
• Licensing agreements.
Operations and Maintenance (O&M) Documentation title of the project and the names and
contact information for the architect or engineer, ICT systems designer, and ICT systems
contractor
A _____________________ outlines the processes required to certify and deliver a complete
and functioning system to the client. commissioning plan
A commissioning plan should document: • Administration:
- Labeling of all components.
- O&M documentation.
• Cleaning.
• Testing, adjusting, and settings.
• Training client personnel.
• Warranty time period and licensing.
The ________ ______ is a detailed connection schematic plan to facilitate connecting active
components to the infrastructure. patching matrix
, Patching Matrix Contents • Horizontal and backbone cable ports.
• Patch cable.
• Equipment cord.
• Wire cross connect.
• Optical fiber jumper.
• Coaxial jumpers.
___________ are used to visually document critical components at completion of installation.
Photographs
Required Photographs • Firestop locations.
• Bonding (grounding).
• Hidden structural items.
• Initial rack completion.
• Life safety elements.
• Installation issues.
The T series drawings include: • T0—Campus or site plans: Exterior pathways and
interbuilding systems.
• T1—Layout of complete building per floor: Serving zone boundaries, backbone
distribution systems, and horizontal pathways.
• T2—Serving zones: Work area outlet locations and cable IDs.