MSgt Carlson said, "This is the beginning of the creative stage, where the carefully laid project
plans are turned into tangible deliverables."
MSgt Carlson's comments BEST explain which of the following stages of project management?
Execution
MSgt Livingston said, "This stage provides you, your team and stakeholders with an opportunity
to evaluate how successful the project was and what lessons were learned during the process."
MSgt Livingston's comments BEST explain which of the following stages of project
management? Closure
MSgt Landry said, "This project management stage is all about giving the project a relatively
broad definition and establishing whether or not it is feasible."
MSgt Landry's comments BEST explain which of the following stages of project management?
Initiation
, Following resources, this part is next. There shouldn't be more than 10 to 13 total tasks on it,
including the deadline date for the final deliverable.
This statement BEST describes which of the following parts of a Project Plan? The
milestone schedule
This is at the end of the project, which shouldn't run more than a page or so. It should outline
the highlights of the project.
This statement BEST describes which of the following parts of a Project Plan? The
executive summary
Start by including this into your team composition table. In this table, list each project team
member and his or her status (regular or ad hoc member) and each stakeholder and his or her
status.
This statement BEST describes which of the following parts of a Project Plan? Resources
This is the first section of the detailed plan. You must write it down in description in which you
describe the final deliverable in terms the customer can understand.
This statement BEST describes which of the following parts of a Project Plan? The scope
plan