100% de satisfacción garantizada Inmediatamente disponible después del pago Tanto en línea como en PDF No estas atado a nada 4,6 TrustPilot
logo-home
Examen

PJM Practice Exam Questions And Answers |Latest 2025 | Guaranteed Pass.

Puntuación
-
Vendido
-
Páginas
34
Grado
A+
Subido en
23-03-2025
Escrito en
2024/2025

©THESTAR 2025 ALL RIGHTS RESERVED 11:41 AM A+ 1 | P a g e PJM Practice Exam Questions And Answers |Latest 2025 | Guaranteed Pass. A Heavy Load Voltage Schedule Warning is typically issued ___ prior to actual implementation. - Answerc. 4 hours The following would be considered non-critical plant load (Select 2) - AnswerA. Office Area Air Conditioners C. Lighting During a Cold Weather Alert, PJM will take which of the actions - AnswerD. Assume an unavailability rate for schedule generation When PJM issues a High System Voltage Message, the GO should have its units operate at: - AnswerB. The lower end of their voltage bandwidth ©THESTAR 2025 ALL RIGHTS RESERVED 11:41 AM A+ 2 | P a g e What would the reportable Emergency Reducible Generation be if the Generator Output is 400 MW, Economic Min is 225 MW and the Emergency Min is 175 MW - AnswerC. 50 MW PJM can issue the Deploy All Resources Action for - AnswerD. The entire RTO, specific Control Zones, or a subset of a Control Zone if transmission limitations exist PJM has issued a Minimum Generation Alert. Your current generation is 200 MW. The Economic Minimum is 150 MW and the Emergency Min is 125 MW. How much ERG should be reported for this unit? - AnswerB. 25MW Which of the following steps would PJM take as part of initiating Conservative Operations? (Select 2) - AnswerA. Perform job studies looking at the loss of multiple pieces of equipment as a single event C. Initiate additional off-cost operation to limit or reduce flows across critical interfaces The purpose of the Deploy All Resources Action is to instruct all generating resources to be on line and at full output ____ - AnswerD. Immediately upon receipt of dispatch instructions ©THESTAR 2025 ALL RIGHTS RESERVED 11:41 AM A+ 3 | P a g e Under the National Terrorism Advisory System (NTAS) there are two types of alerts: Elevated Threat Alert and - AnswerA. Imminent Threat Alert What is the requested response time for members to reply to a request for SSR data? - AnswerA. 10 minutes You are a Generation Owner with the following units. PJM has just requested a Supplementary Status Report (SSR). what do you report as your total "On Cost" Steam Capacity U1: ECO max, 145 - EMR max 145 Current output 140 U2 ECO max, 550 - EMR max 145 Current output 400 U3 ECO max, 400, EMR max 410 Current output - Answer1095MW Why does PJM require an additional notification time of Unit testing 30 minutes prior to the GO/MOC performing the reactive capability testing? - AnswerC. To allow PJM and TOs to make adjustments to system voltages prior to test When an outage requires verbal notification to PJM which PJM personnel should be contacted? - AnswerB. Master Coordinator

Mostrar más Leer menos
Institución
PJM
Grado
PJM











Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
PJM
Grado
PJM

Información del documento

Subido en
23 de marzo de 2025
Número de páginas
34
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

©THESTAR 2025 ALL RIGHTS RESERVED 11:41 AM A+




PJM Practice Exam Questions And Answers
|Latest 2025 | Guaranteed Pass.




A Heavy Load Voltage Schedule Warning is typically issued ___ prior to actual implementation. -

Answer✔c. 4 hours




The following would be considered non-critical plant load (Select 2) - Answer✔A. Office Area Air

Conditioners

C. Lighting




During a Cold Weather Alert, PJM will take which of the actions - Answer✔D. Assume an

unavailability rate for schedule generation




When PJM issues a High System Voltage Message, the GO should have its units operate at: -

Answer✔B. The lower end of their voltage bandwidth




1|Page

, ©THESTAR 2025 ALL RIGHTS RESERVED 11:41 AM A+


What would the reportable Emergency Reducible Generation be if the Generator Output is 400

MW, Economic Min is 225 MW and the Emergency Min is 175 MW - Answer✔C. 50 MW




PJM can issue the Deploy All Resources Action for - Answer✔D. The entire RTO, specific Control

Zones, or a subset of a Control Zone if transmission limitations exist




PJM has issued a Minimum Generation Alert. Your current generation is 200 MW. The

Economic Minimum is 150 MW and the Emergency Min is 125 MW. How much ERG should be

reported for this unit? - Answer✔B. 25MW




Which of the following steps would PJM take as part of initiating Conservative Operations?

(Select 2) - Answer✔A. Perform job studies looking at the loss of multiple pieces of equipment

as a single event




C. Initiate additional off-cost operation to limit or reduce flows across critical interfaces




The purpose of the Deploy All Resources Action is to instruct all generating resources to be on

line and at full output ____ - Answer✔D. Immediately upon receipt of dispatch instructions




2|Page

, ©THESTAR 2025 ALL RIGHTS RESERVED 11:41 AM A+


Under the National Terrorism Advisory System (NTAS) there are two types of alerts: Elevated

Threat Alert and - Answer✔A. Imminent Threat Alert




What is the requested response time for members to reply to a request for SSR data? -

Answer✔A. 10 minutes




You are a Generation Owner with the following units. PJM has just requested a Supplementary

Status Report (SSR). what do you report as your total "On Cost" Steam Capacity




U1: ECO max, 145 - EMR max 145 Current output 140

U2 ECO max, 550 - EMR max 145 Current output 400

U3 ECO max, 400, EMR max 410 Current output - Answer✔1095MW




Why does PJM require an additional notification time of Unit testing 30 minutes prior to the

GO/MOC performing the reactive capability testing? - Answer✔C. To allow PJM and TOs to

make adjustments to system voltages prior to test




When an outage requires verbal notification to PJM which PJM personnel should be contacted?

- Answer✔B. Master Coordinator




3|Page

, ©THESTAR 2025 ALL RIGHTS RESERVED 11:41 AM A+


One of the leading causes of the 1999 Low Voltage event in PJM was ___ - Answer✔B. PJM's

EMS at that time had only nameplate D-curve data for




With whom does PJM share the results of generation reactive capability tests? - Answer✔A.

The affected TO




With the exception of intermittent resources, Over-excited (Lagging) test results are the values

of MVAR output that can be sustained for how long? - Answer✔D. 60 min




During the PJM Peak Period Maintenance Season whit is the max amount of consecutive days

the outage can last? - Answer✔C. 9




When PJM requests a Reactive Reserve Check (RRC), how does the GO/MOC report limitations

or restrictions on their unit which would prevent it from being able to follow it's reactive

capability curve as recorded in eDART - Answer✔A. By notifying the effect TO




What is the min time needed to submit a reactive capability test ticket via eDARt prior to

performing the test? - Answer✔C. 3 business days




4|Page
$12.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
TheStar Florida State University
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
611
Miembro desde
2 año
Número de seguidores
179
Documentos
24244
Última venta
2 días hace
Stuvia Prodigy

Tested, Verified and Updated Study Materials with 100% Guaranteed Success.

3.8

122 reseñas

5
58
4
22
3
21
2
4
1
17

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes