What is the length of time the architect and contractor have to review shop drawings? -
Answer✔Within a reasonable time
What is meant by a waiver of subrogation in and owner-architect contract? - Answer✔The
architect and the owner cannot she each other for items covered by their property insurances
What is the typical order of the design process from earliest to latest in which they occur? -
Answer✔SD, DD, CD, B&N, CA
Traditionally what phase of construction requires most of the architect's time? - Answer✔CD
External failure costs - Answer✔-incurred to remedy defects discovered by customers
1|Page
, ©THESTAR 2025 ALL RIGHTS RESERVED 11:41 AM A+
-occur when products or services that fail to reach design quality standards are not detected
until after transfer to the customer
According to A201 "the work" includes what? - Answer✔-Labor
-materials
-completed portions of the project
-partially completed portions of the project
What techniques and tools can the project manager use to ensure that the budgeted time for a
particular design project is strictly adhered to? - Answer✔-use project monitoring chart to
monitor budgeted time against actual time
-create full wall schedule with the whole team including client
At what stage of the process should the architect first involve consultants? - Answer✔As early
as possible
What are potential effects of shortening a project schedule? - Answer✔-higher costs
-lower quality project
-higher design costs