Ans You are the project manager on a project where the scope has expanded. The change has been approved by the change control board (CCB). What steps must you take to acknowledge the new scope? Each correct answer represents a complete solution. Choose all that apply. A. Communicate the change to stakeholders and team members. B. Update the project management plan. C. Log the request on the change request log. D. Submit a change request. A scrum meeting, which is part of the Agile methodology. Ans In which meeting do team members come prepared to answer the following three questions? What work they completed yesterday? What work they will complete today? What obstacles stand in their way? A. A clear chain of command. B. Growth potential and a career path for employees. Here are the advantages of the functional organization: Growth potential and a career path for em

Mostrar más Leer menos
Institución
Grado










Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
Grado

Información del documento

Subido en
10 de marzo de 2025
Número de páginas
22
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

WGU C176 Pre-Assessment questions with verified
answers
Ans✓✓✓ You are the project manager on a project where the scope has
expanded. The change has been approved by the change control board (CCB).
What steps must you take to acknowledge the new scope?


Each correct answer represents a complete solution. Choose all that apply.


A. Communicate the change to stakeholders and team members.
B. Update the project management plan.
C. Log the request on the change request log.
D. Submit a change request.


A scrum meeting, which is part of the Agile methodology. Ans✓✓✓ In which
meeting do team members come prepared to answer the following three
questions?
What work they completed yesterday?
What work they will complete today?
What obstacles stand in their way?


A. A clear chain of command.
B. Growth potential and a career path for employees.


Here are the advantages of the functional organization:
Growth potential and a career path for employees

,The opportunity for those with unique skills to flourish
A clear chain of command (each staff member has one supervisor—the functional
manager)
Answers D and C are incorrect. Here are the disadvantages of the functional
organization:
Project managers have limited to no authority.
Multiple projects compete for the same limited resources.
Resources are generally committed part-time to the project rather than full-time.
Issue resolution follows the department chain of command.
Project team members are loyal to the functional manager. Ans✓✓✓ What are
the advantages of the functional organization?


Each correct answer represents a complete solution. Choose all that apply.


A. A clear chain of command.
B. Growth potential and a career path for employees.
C. Issue resolution follows the department chain of command.
D. Full-time resources are assigned to


A. Adjourning
B. Storming
D. Forming
F. Norming Ans✓✓✓ Which of the following are the stages of development that
project teams progress through?


Each correct answer represents a complete solution. Choose all that apply.

, A. Adjourning
B. Storming
C. Acquiring
D. Forming
E. Compromising
F. Norming
G. Negotiating


A. Administering the change control process
C. Performing quality assurance/governance activities
D. Performance measuring and reporting


Here are the activities involved in the monitoring and controlling process:
Monitoring the risks/issues log
Performance measuring and reporting
Performing quality assurance/governance activities
Administering the change control process
Monitoring the budget Ans✓✓✓ What are the activities involved in the
monitoring and controlling process?


Each correct answer represents a complete solution. Choose all that apply.


A. Administering the change control process
B. Defining the high-level risks
$18.49
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
cracker Chamberlain School Of Nursing
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
2016
Miembro desde
3 año
Número de seguidores
1342
Documentos
46956
Última venta
1 hora hace
✨ Cracker – Verified Study Powerhouse

Welcome to your shortcut to academic and certification success. I'm Cracker, a trusted top seller I specialize in high-quality study guides, test banks, certification prep, and real-world exam material all tailored to help you pass fast and score high.

3.8

370 reseñas

5
162
4
84
3
53
2
22
1
49

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes