HOISTING LICENSE MA- 2A QUESTIONS AND
ANSWERS
In the event of a death occurring what should you do, who should be notified, and
when? - Answers - The scene of the accident should be untouched and The Department
of Public Safety, District Engineering Office should be notified within one hour of the
accident.
Injury Records-
When should they be recorded, and who should have a copy of them? - Answers - In
the event of an injury occurring requiring hospitalization or immediate medical attention
by a doctor or nurse must be recorded. These records should be available at the project
site for the inspector. A copy of this record should also be sent to the Engineers section
of the Department of Public Safety immediately after treatment.
License Classification-
This refers to any of the four general types of hoisting licenses which are: - Answers -
Hoisting, excavating, electric, and air.
Welding and Cutting - Answers - All welding and cutting on hoisting machinery shall be
performed in accordance with the requirements of 1998 Section IX of the American
Society of Mechanical Engineers Code.
Operating Procedures-
The operator shall not... - Answers - participate in anything that will distract them while
they are engaging in the operation of the hoisting equipment.
Operating Procedures-
If an operator is mentally or physically unfit... - Answers - they shall not engage in the
operation of the hoisting equipment.
Operating Procedures-
Prior to starting any hoisting equipment the operator must do what? - Answers - Take a
complete walk around the equipment to verify people are clear of the equipment as well
as a safe ways away.
Operating Procedures-
Prior to operating hoisting equipment with a rotating superstructure, barricades, warning
lines, or other what should you do? - Answers - you must use approved procedures to
prevent entry into a superstructures radius.
Operating Procedures-
ANSWERS
In the event of a death occurring what should you do, who should be notified, and
when? - Answers - The scene of the accident should be untouched and The Department
of Public Safety, District Engineering Office should be notified within one hour of the
accident.
Injury Records-
When should they be recorded, and who should have a copy of them? - Answers - In
the event of an injury occurring requiring hospitalization or immediate medical attention
by a doctor or nurse must be recorded. These records should be available at the project
site for the inspector. A copy of this record should also be sent to the Engineers section
of the Department of Public Safety immediately after treatment.
License Classification-
This refers to any of the four general types of hoisting licenses which are: - Answers -
Hoisting, excavating, electric, and air.
Welding and Cutting - Answers - All welding and cutting on hoisting machinery shall be
performed in accordance with the requirements of 1998 Section IX of the American
Society of Mechanical Engineers Code.
Operating Procedures-
The operator shall not... - Answers - participate in anything that will distract them while
they are engaging in the operation of the hoisting equipment.
Operating Procedures-
If an operator is mentally or physically unfit... - Answers - they shall not engage in the
operation of the hoisting equipment.
Operating Procedures-
Prior to starting any hoisting equipment the operator must do what? - Answers - Take a
complete walk around the equipment to verify people are clear of the equipment as well
as a safe ways away.
Operating Procedures-
Prior to operating hoisting equipment with a rotating superstructure, barricades, warning
lines, or other what should you do? - Answers - you must use approved procedures to
prevent entry into a superstructures radius.
Operating Procedures-