100% de satisfacción garantizada Inmediatamente disponible después del pago Tanto en línea como en PDF No estas atado a nada 4,6 TrustPilot
logo-home
Examen

OVERALL EQUIPMENT EFFECTIVENESS EXAM QUESTIONS AND ACCURATE ANSWERS 2024/2025 | VERIFIED

Puntuación
-
Vendido
-
Páginas
10
Grado
A+
Subido en
24-02-2025
Escrito en
2024/2025

OVERALL EQUIPMENT EFFECTIVENESS EXAM QUESTIONS AND ACCURATE ANSWERS 2024/2025 | VERIFIED

Institución
OVERALL EQUIPMENT EFFECTIVENESS
Grado
OVERALL EQUIPMENT EFFECTIVENESS









Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
OVERALL EQUIPMENT EFFECTIVENESS
Grado
OVERALL EQUIPMENT EFFECTIVENESS

Información del documento

Subido en
24 de febrero de 2025
Número de páginas
10
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

OVERALL EQUIPMENT EFFECTIVENESS EXAM QUESTIONS AND ACCURATE
ANSWERS 2024/2025 | VERIFIED
5 Why Analysis - ✔️✔️A simple process originally created by Sakichi Toyoda at the Toyota Motor
Company for identifying the root cause behind a particular problem. Start with a problem definition, and
keep asking "why" until the root cause is uncovered.


5S - ✔️✔️A Lean Manufacturing process that creates an organized work area. 5S has five steps: Sort
(eliminate unneeded items), Set (organize remaining items), Shine (clean and inspect the work area),
Standardize (document standards for the area), Sustain (apply and audit the standards).


Actual Cycle Time - ✔️✔️The actual time to produce one part. In OEE, calculated as Run Time divided
by Total Count. Used in calculating OEE Performance. A variation of the calculation uses Actual Run Rate
instead.


Actual Run Rate - ✔️✔️The actual rate of production, when it is running. In OEE, calculated as Total
Count divided by Run Time. Used in calculating OEE Performance. A variation of the calculation uses
Actual Cycle Time instead.


All Time - ✔️✔️24 hours in a day, 7 days in a week. All time refers to every minute of every day.


Andon - ✔️✔️Indicator above production line to signal production conditions. Often uses
green/yellow/red colors to indicate status.


Autonomous Maintenance - ✔️✔️A process from TPM (Total Productive Maintenance) for improving
machine OEE by engaging operators to complete routine maintenance, inspection, and lubrication
activities.


Availability Loss - ✔️✔️One of the three OEE Losses. Availability takes into account Equipment Failures
and Setup and Adjustments. An Availability score of 100% means that the process is always running
during Planned Production Time.


Best Practice - ✔️✔️Methods that are considered "state of the art" by the most respected in an
industry. Successful companies use different methods than unsuccessful companies.

, Brainstorming - ✔️✔️A process for creating an expanded world of ideas and possibilities. Brian
storming is a divergent problem solving process that is intended to create a broad range of ideas that can
then be refined by a root cause process.


Breakdowns - ✔️✔️A type of Unplanned Stop where time is lost due to Equipment Failure (one of the
Six Big Losses). Breakdowns are a type of Unplanned Stop and affect OEE Availability.


Breaks - ✔️✔️Unproductive time where the process is scheduled not to run because the crew is
scheduled to be away from the line. Breaks are typically excluded from OEE calculations.


Capacity - ✔️✔️The maximum amount of production available if equipment is fully productive (running
at 100% OEE), for All Time (24/7).


Changeover - ✔️✔️The manufacturing process is scheduled for production and is not running because
of a planned Setup, Make Ready, or Adjustment event. Changeovers are a type of Planned Stop and
affect OEE Availability.


Constraint - ✔️✔️The step of the manufacturing process that acts as a bottleneck to the throughput of
the entire process. OEE should always be measured at the constraint as it is the slowest step in the
process.


Countermeasures - ✔️✔️An action to counter or mitigate a manufacturing loss. A manufacturing loss
may benefit from multiple countermeasures including immediate actions to prevent the loss from
getting worse, short term fixes and long term root cause fixes.


Cycle Time - ✔️✔️The time to produce one part. Inverse of Run Rate.


Cycle Time Analysis - ✔️✔️Tool used to better understand issues that affect Performance. Important to
automate logging of Cycle Times for later analysis.


Defect - ✔️✔️Any part that is not right first time. Defects may be reworked, or scrapped. All defects are
a loss to OEE Quality.


Design Cycle Time - ✔️✔️See Ideal Cycle Time.
$12.98
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor
Seller avatar
DrRashford

Conoce al vendedor

Seller avatar
DrRashford Teachme2-tutor
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
0
Miembro desde
1 año
Número de seguidores
0
Documentos
100
Última venta
-

0.0

0 reseñas

5
0
4
0
3
0
2
0
1
0

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes