Required amount of mix for ignition samples? - Correct Answer-Depends on the mix. SP & FC 5, 9.5, 12.5 are 1500g. SP 19 is 2000g Asphalt burns off at what temp - Correct Answer-538°C (1000°F) The furnace must be capable of what temperature - Correct Answer-650°C (1200°F) Flasks should be calibrated at what temperature and how often? - Correct Answer-77 +/ 2°F of water and once a month or 0.4 grams of dry weight How many parts of wetting agent to water - Correct Answer-1ml wetting agent to 1000ml water Proper weight of mix for gyratory compactor - Correct Answer-Around g. Determined through the mix design process to achieve the height of 115 +/- 5mm

Vista previa del contenido

FDOT Asphalt Plant Level 1
Required amount of mix for ignition samples? - Correct Answer-Depends on the mix. SP
& FC 5, 9.5, 12.5 are 1500g. SP 19 is 2000g

Asphalt burns off at what temp - Correct Answer-538°C (1000°F)

The furnace must be capable of what temperature - Correct Answer-650°C (1200°F)

Flasks should be calibrated at what temperature and how often? - Correct Answer-77 +/
2°F of water and once a month or >0.4 grams of dry weight

How many parts of wetting agent to water - Correct Answer-1ml wetting agent to
1000ml water

Proper weight of mix for gyratory compactor - Correct Answer-Around 4500 - 5000g.
Determined through the mix design process to achieve the height of 115 +/- 5mm

Required amount of mix for Gmm (rice) samples? - Correct Answer-2000-2200g total or
1000-1100 grams individually for two flasks

The vacuum applied to flasks for GMM - Correct Answer-30 +/- 2mm

Vacuum pressure for GMM must be reached within - Correct Answer-2 minutes

The Orbital Shaker must oscillate at - Correct Answer-270 +/- 10 rpms

The vacuum and oscillating test for GMM then continues for how long when it reaches
target pressure - Correct Answer-15 +/- 2minutes

Gyratory compaction angle is - Correct Answer-an internal angle of 1.16 +/- .02 degrees

Ram pressure for gyratory compaction is - Correct Answer-600 +/- 18 kpA perpendicular
to the axis

RPM the gyratory compactor operates at - Correct Answer-30 +/- .5 gyrations a minute

Gyratory (GMB) and Rice (GMM) samples must be conditioned at what temp and for
how long - Correct Answer-compaction temp +/- 9 for 1 hour +/- 5minutes and mix
should be within +/-20° of compaction temp

The mold and base plate for the gyratory compactor should be in the oven for how long
- Correct Answer-30 to 60 minutes

, Target specific height for pills - Correct Answer-115.0mm +/- 5mm

How do you determine aggregate is dry? - Correct Answer-Weigh the material every 15
minutes when it has lost less than 0.5 grams is it considered dry

Bulk specific gravity (pill) water weight is determined after - Correct Answer-4 +/- 1
minute

When the pill is removed from the water it should be blotted and weighed in what time
and how - Correct Answer-5 seconds with a top and bot flip and then a roll roll
The towel should be damp

Formula for GMB (BSG) - Correct Answer-Dry ÷ (SSD - Water Weight)
Round to 3 decimal places

Calculating air voids - Correct Answer-(Gmm - Gmb ÷ Gmm) × 100

For Asphalt Binders PG stands for what? - Correct Answer-Performance Graded

What do the numbers mean for an asphalt binder? ex: PG 67-22 - Correct Answer-67 is
the average 7 day high temp in Celsius and 22 is the negative low temp in Celsius

ATPB stands for and is used in what? - Correct Answer-Asphalt Treatsd Permeable
Base
Used under concrete for drainage

Friction Courses are required on what jobs based on AADT and Design Speed - Correct
Answer-AADT > 3000
Design Speed > 35 mph

A PMA asphalt binder stands for what? - Correct Answer-Polymer Modified Asphalt

An ARB asphalt binder stands for what? - Correct Answer-Asphalt Rubber Binder

Subgrade requires an LBR of what? - Correct Answer-40

When do you sample tack? - Correct Answer-During unloading when it reaches 1/3 of
the load

What do you do first before sampling tack or binder? - Correct Answer-Discard the first
gallon to clear the line

What is the goal of sampling? - Correct Answer-To be done so randomly to avoid bias
and creat uniform representative samples

Información del documento

Subido en
22 de febrero de 2025
Número de páginas
5
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas
$8.49

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
quizletquizizzy
5.0
(1)
Vendido
9
Seguidores
0
Artículos
517
Última venta
5 meses hace


Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes