Questions and CORRECT Answers
Refined topics and search results - CORRECT ANSWER - Two feature options appear
once you click on an item in a reference search image. Which ones are they?
Item activity (ACT) Field - CORRECT ANSWER - Which quick entry field determines
the items unit price by describing exactly what is to happen to that specified item
False - CORRECT ANSWER - When an estimate is marked completed you can still
modify it
True - CORRECT ANSWER - In some instances you may leave inspection results if they
are correct for the scope of the estimate
Download the estimate from the cloud which changes it back to in progress - CORRECT
ANSWER - If you want to make changes to an estimate that has a status of completed you
must
Properties - CORRECT ANSWER - Once a roof has been placed the roof tight can be
changed in the ———-window
P - CORRECT ANSWER - What variable can be use to place drip edge around the entire
perimeter of a roof
True - CORRECT ANSWER - The square break tool can be used on roofs the same way it
is used on rooms
subgroup - CORRECT ANSWER - If an overbilled roof is not a _________of the main
roof then those quantities will not be calculated with the main roof
, Lock the dimensions of the opposing roof face - CORRECT ANSWER - When adding in a
Extension to the eve of a roof how do you keep the ridge from moving
False - CORRECT ANSWER - The related items search method and the similar item
search method can be used in exactly the same way
Carpet vinyl sheet goods shingles - CORRECT ANSWER - What three types of items do
not have waist automatically included in the cost of the item
Variable times 1.15 - CORRECT ANSWER - What is the calculation to add 15% waste
manually to a line item
True - CORRECT ANSWER - To move your cursor from one Phil to another in quick
entry tap the tab key successfully on your keyboard
True - CORRECT ANSWER - When you're cursor is in a field that has a drop-down arrow
press the on your keyboard to view and expanded list of options
enter - CORRECT ANSWER - From any quick entry field press _______ on your
keyboard to move your cursor to the next line to begin adding
Items
False - CORRECT ANSWER - Marking an estimate completed is necessary to upload it
back to exact analysis
True - CORRECT ANSWER - When you change the status of an estimate to completed the
inspection will check for common estimating mistakes
Change the estimate status to in progress - CORRECT ANSWER - If you want to make
changes to an estimate that has a status of completed you must