MGMT 404 Test 1 and 2 questions with
correct answers
We have a project (Cardinal), with these activities in days: Activity A with duration 4 and no precedents.
Activity B with duration 15 and predecessor. A, Activity C with duration 9 and predecessor. A, Activity D
with duration 2 and predecessor B, Activity E has duration 6 and predecessors B and C, Activity F has
duration 4 and predecessor D, and Activity G has duration 15 and predecessors of E and F. Draw this to
answer the following questions. How long is this project scheduled to take? - CORRECT ANSWER-
✔✔✅40 Days
From question #1, what is the EF for Node E? - CORRECT ANSWER-✔✔✅25
From question #1, what is the LF for Node E? - CORRECT ANSWER-✔✔✅25
What is the critical path from #1? - CORRECT ANSWER-✔✔✅A~B~E~G
From question #1, what is the EF for Node D? - CORRECT ANSWER-✔✔✅21
From question #1, what is the ES for Node E? - CORRECT ANSWER-✔✔✅19
From question #1, what is the LS for Node C? - CORRECT ANSWER-✔✔✅10
From question #1, what is the slack in node E? - CORRECT ANSWER-✔✔✅0 Day(s)
From question #1, what is the LF for Node D? - CORRECT ANSWER-✔✔✅21
From question #1, what is the slack in node D? - CORRECT ANSWER-✔✔✅0 day(s)
From question #1, what is the ES for Node C? - CORRECT ANSWER-✔✔✅4
, From historical data, we know it takes 45 minutes to paint a 100 square foot area. We have to paint a
800 square foot area. How long should we put for the duration of this activity? - CORRECT ANSWER-
✔✔✅360 minutes
What are the components in the lowest level of the WBS hierarchy collectively called? - CORRECT
ANSWER-✔✔✅Work Packages
Which estimating technique uses a similar project to predict how long the current project will take to
complete? - CORRECT ANSWER-✔✔✅Analogous estimating
Ashley, a project manager in your company, is falling behind on the project schedule. She has elected to
crash the project. What is crashing? - CORRECT ANSWER-✔✔✅Adding additional project resources to
the project activities
Which of the following is normally NOT one of the traditional components of the triple constraint? -
CORRECT ANSWER-✔✔✅Accepted by the customer
Walking down the hallway, you heard a program manager saying to a project manager, You need the
performance reports to run this process. Which process is the program manager referring to? - CORRECT
ANSWER-✔✔✅Monitor and Control Project Work
Which organizational structure generally retains team members on it long after they are needed? -
CORRECT ANSWER-✔✔✅Projectized
In a RACI chart, what does the C stand for? - CORRECT ANSWER-✔✔✅Consult
Which of the following is FALSE concerning the critical path in a network? - CORRECT ANSWER-✔✔✅It
is the path that always contains the greatest number of activities
Which of the following is NOT one of the ten project management knowledge areas? - CORRECT
ANSWER-✔✔✅Project team management
correct answers
We have a project (Cardinal), with these activities in days: Activity A with duration 4 and no precedents.
Activity B with duration 15 and predecessor. A, Activity C with duration 9 and predecessor. A, Activity D
with duration 2 and predecessor B, Activity E has duration 6 and predecessors B and C, Activity F has
duration 4 and predecessor D, and Activity G has duration 15 and predecessors of E and F. Draw this to
answer the following questions. How long is this project scheduled to take? - CORRECT ANSWER-
✔✔✅40 Days
From question #1, what is the EF for Node E? - CORRECT ANSWER-✔✔✅25
From question #1, what is the LF for Node E? - CORRECT ANSWER-✔✔✅25
What is the critical path from #1? - CORRECT ANSWER-✔✔✅A~B~E~G
From question #1, what is the EF for Node D? - CORRECT ANSWER-✔✔✅21
From question #1, what is the ES for Node E? - CORRECT ANSWER-✔✔✅19
From question #1, what is the LS for Node C? - CORRECT ANSWER-✔✔✅10
From question #1, what is the slack in node E? - CORRECT ANSWER-✔✔✅0 Day(s)
From question #1, what is the LF for Node D? - CORRECT ANSWER-✔✔✅21
From question #1, what is the slack in node D? - CORRECT ANSWER-✔✔✅0 day(s)
From question #1, what is the ES for Node C? - CORRECT ANSWER-✔✔✅4
, From historical data, we know it takes 45 minutes to paint a 100 square foot area. We have to paint a
800 square foot area. How long should we put for the duration of this activity? - CORRECT ANSWER-
✔✔✅360 minutes
What are the components in the lowest level of the WBS hierarchy collectively called? - CORRECT
ANSWER-✔✔✅Work Packages
Which estimating technique uses a similar project to predict how long the current project will take to
complete? - CORRECT ANSWER-✔✔✅Analogous estimating
Ashley, a project manager in your company, is falling behind on the project schedule. She has elected to
crash the project. What is crashing? - CORRECT ANSWER-✔✔✅Adding additional project resources to
the project activities
Which of the following is normally NOT one of the traditional components of the triple constraint? -
CORRECT ANSWER-✔✔✅Accepted by the customer
Walking down the hallway, you heard a program manager saying to a project manager, You need the
performance reports to run this process. Which process is the program manager referring to? - CORRECT
ANSWER-✔✔✅Monitor and Control Project Work
Which organizational structure generally retains team members on it long after they are needed? -
CORRECT ANSWER-✔✔✅Projectized
In a RACI chart, what does the C stand for? - CORRECT ANSWER-✔✔✅Consult
Which of the following is FALSE concerning the critical path in a network? - CORRECT ANSWER-✔✔✅It
is the path that always contains the greatest number of activities
Which of the following is NOT one of the ten project management knowledge areas? - CORRECT
ANSWER-✔✔✅Project team management