Class A/B Operator for Underground Storage Tank Exam Questions and Answers New owners of an existing UST system shall register the UST system with DEQ/LARA within what period from date of ownership? - ANSWER -30 days UST systems with cathodic protection should be inspected for proper operation by a qualified cathodic protection tester on the following schedule: - ANSWER -Every three years UST systems with impressed current cathodic protection systems must be inspected at a minimum: - ANSWER -Every 60 days Within what period after a repair should a cathodically protected UST system be tested to ensure it is working properly? - ANSWER -6 months Pressurized underground piping that routinely contains regulated substances shall be monitored for releases in a manner that meets what requirements? - ANSWER -Be equipped with a line leak detector, and have an annual line tightness test A suspected release must be confirmed to the DEQ/LARA within: - ANSWER -7 days What actions are required in MUSTR when there is a spill or overfil of petroleum or hazardouz substances that result in a release into groundwater, surface water, or substance soils? - ANSWER -Notify DEQ/LARA of a confirmed release, Immediately clean up the spill or overfill, and Contain the spill To permanently close a tank, an owner and operator shall: - ANSWER -Remove the tank from the ground, Fill with an inert solid if removal jeopardizes the building structure integrity, and Empty and clean the tank by removing all liquids and accumulated sludge and purge it of all vapors If you have 100 or fewer tanks, financial responsibility is required in the aggregate the amount of: - ANSWER -$1 Million Petroleum marketers are required to have finanical responsibility to cover X dollars per occurence. X is.... - ANSWER -$1 Million Can an owner use pollution liability insurance as a means of financial responsibility? - ANSWER -Yes An automatic tank gauge must be able to detect a leak of X gallons per hour. X is: - ANSWER -0.2 gallons per hour Statistical Inventory reconciliation (SIR) analyzes the following as a means of leak detection: - ANSWER -Inventory, Delivery and Dispensing Manual tank gauging can be used as the 'sole' means of a leak detection for tanks that are X gallons or less in capacity. X is: - ANSWER -550 gallons Check if the following statement is true or false: "A third party evaluation of a statistical inventory reconciliation is good for any type of tank and product." - ANSWER -False Automatic line leak detectors must be able to detect a leak of at least X gallons per hour at a line pressure of 10 psi witin one hour. X is: - ANSWER -3 gallons per hour Line testing of piping shall be capable of detecting X gallons per hour leak rate at 1 and a half times the operating pressure. X is: - ANSWER -0.1 gallons per hour What actions are not appropriate when when the owner/operator becomes aware of a spill or overfill? - ANSWER -Drain the spill to the storm sewer or nearby ditch Upon confirmation of a release to the soil/groundwater/surface water the operator shall: - ANSWER -Report the release to the DEQ within 24 hours, by fax or phone A Class B operator shall not be responsible for more than the following facilities: - ANSWER -45 facilities What is the minimum frequency of site inspections to assure operational compliance? - ANSWER -Quarterly If a facility has been determined by the DEQ inspector to be out of compliance with the significant operational compliance requirements, the DEQ shall retrain: - ANSWER -The class A operator of the facility When planning to permanently close a UST system, the DEQ must be notified not less than: - ANSWER -30 days Upon permanent Removal of an UST system, the operator shall: - ANSWER -Notify the DEQ within 30 days with an amended registration form The operator shall notify the DEQ of a confirmed release upon removal of an UST and visual evidence showing: - ANSWER -Either there is visibly contaminated groundwater in the tank cavity or there is visibly contaminated soil in the tank cavity and/or soil removed from the tank cavity Upon removal of an UST where there is no visual or olfactoryevidence of a release , the operator shall: - ANSWER -Take soil samples, analyze them, and then send the site assessment results to the DEQ for a determination A leak should be suspected in 1,560 gallon tank if the variation between the beginning and ending manual tank gauging liquid level measurements exceeds the weekly standard of X gallons. X is: - ANSWER -26 gallons The class B operator should inspect the UST system for operational compliance status at a minimum: - ANSWER -Every quarter Release detection records of sampling, testing, or monitoring shall be maintained for: - ANSWER -2 years When a tank that has been installed for less than 10 years is upgraded with the cathodic protection, tightness test(s) are required as follows: - ANSWER -Tightness tests should be conducted before the installation of cathodic protection and 3-6 months after the installation of the cathodic protection UST systems with impressed current cathodic protection systems must also be inspected at a minimum of: - ANSWER -Every 60 days Product inventory control shall be conducted monthly to detect a release of not less than X% of flow through plus 130 gallons a monthly basis. X% is: - ANSWER -1% Automatic line leak detector may be used only if the method detects X gallons per hour at 10 pounds per square inch line pressure within one hour. X is: - ANSWER -3 gallons per hour Tank tightness testing, or another test of equivalent performance, shall be capable of detecting X gallon per hour leak rate from any portion of the tank while accounting for the effects of thermal expansion or the contraction of the product, vapor pockets, tank deformation, evaporation or condensation, and the location of the water table. X is: - ANSWER -0.1 gallons per hour MUSTR requires that X soil borings to be taken as close as practical to the bottom of the UST, but no more than 5 feet away from the tank, nor more than 2 feet below the tank. X is: - ANSWER -2 soil borings The results of site assessments conductedper MUSTR R 29.2155 are required to be kept by the owner for not less than X years. X is: - ANSWER -3 years Which National Leak Prevention Association Standard on lining of USTs is adopted by reference in the MUSTR? - ANSWER -631 MUSTR requires what to happen with a UST before it is removed from the ground or closed in place? - ANSWER -Is registered and all fees are paid When using secondary containment with interstitial monitor must be checked at least once every... - ANSWER -30 days

Mostrar más Leer menos
Institución
Class A/B Operator For Underground Storage Tank
Grado
Class A/B Operator for Underground Storage Tank









Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
Class A/B Operator for Underground Storage Tank
Grado
Class A/B Operator for Underground Storage Tank

Información del documento

Subido en
2 de enero de 2025
Número de páginas
7
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

Class A/B Operator for Underground Storage Tank
Exam Questions and Answers

New owners of an existing UST system shall register the UST system with DEQ/LARA
within what period from date of ownership? - ANSWER -30 days

UST systems with cathodic protection should be inspected for proper operation by a
qualified cathodic protection tester on the following schedule: - ANSWER -Every three
years

UST systems with impressed current cathodic protection systems must be inspected at
a minimum: - ANSWER -Every 60 days

Within what period after a repair should a cathodically protected UST system be tested
to ensure it is working properly? - ANSWER -6 months

Pressurized underground piping that routinely contains regulated substances shall be
monitored for releases in a manner that meets what requirements? - ANSWER -Be
equipped with a line leak detector, and have an annual line tightness test

A suspected release must be confirmed to the DEQ/LARA within: - ANSWER -7 days

What actions are required in MUSTR when there is a spill or overfil of petroleum or
hazardouz substances that result in a release into groundwater, surface water, or
substance soils? - ANSWER -Notify DEQ/LARA of a confirmed release, Immediately
clean up the spill or overfill, and Contain the spill

To permanently close a tank, an owner and operator shall: - ANSWER -Remove the
tank from the ground, Fill with an inert solid if removal jeopardizes the building structure
integrity, and Empty and clean the tank by removing all liquids and accumulated sludge
and purge it of all vapors

If you have 100 or fewer tanks, financial responsibility is required in the aggregate the
amount of: - ANSWER -$1 Million

Petroleum marketers are required to have finanical responsibility to cover X dollars per
occurence. X is.... - ANSWER -$1 Million

Can an owner use pollution liability insurance as a means of financial responsibility? -
ANSWER -Yes

An automatic tank gauge must be able to detect a leak of X gallons per hour. X is: -
ANSWER -0.2 gallons per hour

, Statistical Inventory reconciliation (SIR) analyzes the following as a means of leak
detection: - ANSWER -Inventory, Delivery and Dispensing

Manual tank gauging can be used as the 'sole' means of a leak detection for tanks that
are X gallons or less in capacity. X is: - ANSWER -550 gallons

Check if the following statement is true or false: "A third party evaluation of a statistical
inventory reconciliation is good for any type of tank and product." - ANSWER -False

Automatic line leak detectors must be able to detect a leak of at least X gallons per
hour at a line pressure of 10 psi witin one hour. X is: - ANSWER -3 gallons per hour

Line testing of piping shall be capable of detecting X gallons per hour leak rate at 1 and
a half times the operating pressure. X is: - ANSWER -0.1 gallons per hour

What actions are not appropriate when when the owner/operator becomes aware of a
spill or overfill? - ANSWER -Drain the spill to the storm sewer or nearby ditch

Upon confirmation of a release to the soil/groundwater/surface water the operator shall:
- ANSWER -Report the release to the DEQ within 24 hours, by fax or phone

A Class B operator shall not be responsible for more than the following facilities: -
ANSWER -45 facilities

What is the minimum frequency of site inspections to assure operational compliance? -
ANSWER -Quarterly

If a facility has been determined by the DEQ inspector to be out of compliance with the
significant operational compliance requirements, the DEQ shall retrain: - ANSWER -The
class A operator of the facility

When planning to permanently close a UST system, the DEQ must be notified not less
than: - ANSWER -30 days

Upon permanent Removal of an UST system, the operator shall: - ANSWER -Notify the
DEQ within 30 days with an amended registration form

The operator shall notify the DEQ of a confirmed release upon removal of an UST and
visual evidence showing: - ANSWER -Either there is visibly contaminated groundwater
in the tank cavity or there is visibly contaminated soil in the tank cavity and/or soil
removed from the tank cavity

Upon removal of an UST where there is no visual or olfactoryevidence of a release ,
the operator shall: - ANSWER -Take soil samples, analyze them, and then send the site
assessment results to the DEQ for a determination
$8.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
TheExamMaestro Teachme2-tutor
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
121
Miembro desde
1 año
Número de seguidores
5
Documentos
3167
Última venta
6 días hace
Exam Vault

Exam Vault is your trusted destination for high-quality exam materials and study resources. We provide a wide rage of tests and prep guides to help you succeed, whether you're preparing for academic exams, certifications, or professional assessments

3.8

13 reseñas

5
7
4
2
3
1
2
0
1
3

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes