Ladders used to provide access to deck-forming levels must
extend above the formwork at least _____. - ✔✔3 feet
Stringers should be centered on U-heads and top plates to _____.
- ✔✔avoid eccentric loads
Mudsills used to support shores must be sound and _____. -
✔✔rigid
Because of the massive weight of concrete being placed all at
once for one-way solid slabs, the shoring system must be _____.
- ✔✔designed by a structural engineer
One-way solid slabs span parallel lines of support formed by
_____. - ✔✔beams or walls
Two-way beam-and-slab floors normally require support by
beams and walls _____. - ✔✔only at the perimeter
1
©NINJANERD 2024/2025. YEAR PUBLISHED 2024.
, High-rise apartment and office buildings with light floor loads are
often constructed using _____. - ✔✔two-way flat plate slabs
The ribs and slab of one-way joist slabs are cast _____. -
✔✔monolithically
Two-way joist slabs are commonly known as _____. - ✔✔waffle
slabs
In a composite slab, the slab form is _____. - ✔✔corrugated steel
The high-strength steel cables used in posttensioned concrete
construction are called _____. - ✔✔tendons
The live load that shoring must support mostly consists of the
_____. - ✔✔workers and equipment
Standard manufactured dome or square pans are either 19" × 19"
or _____. - ✔✔30" × 30"
Wood I-joists covered with plywood can be used for site-built
_____. - ✔✔wide pan forms