What grade Bar should be used for structures
Grade 60
What coated bar should be used for concrete structures?
Zinc or Epoxy coated
Types of Placement Machines
1: Bucket Hoppers
2: Manuel, Motor Propelled
3: Chutes and Drop Chutes
4: Tremies
5: pumps
Where should concrete be placed on a slope
At the bottom
How far should reinforcing steel be placed away from forms?
3 inches
, Nicet Highway Construction Level 2
Job Site Posting
1: OSHA Regulations
2: Department Of Labor Postings
3: Accident Prevention Postings
4: Safety Plan
5: Accident Reports
6: EEO Poster
7: Job Safety and Health Protection Plan
8: Criminal Code Notice
Inspector Responsibilities Do's
1: Report to EIC
2: Record Measurement, complete reports, communicate quantities to contractor
3: Keep Track of Time and Attendance
4: Inspection Reports, Material Registers
Inspector Responsibilities Dont's
1: Cannot Make subjective interpretations of plans
2: Cannot order work, including provided in construction documents
Where should reinforcing steel tie wire be faced?
Away from the finished surface