VA DEQ SWM Inspector Exam Questions and Answers Graded A+ What is the purpose of the Virginia Stormwater Management Program (VSMP)? To regulate and manage stormwater runoff from new and redevelopment projects to protect water quality. What is the minimum requirement for erosion and sediment control on construction sites under Virginia law? The site must have an approved Erosion and Sediment Control Plan (ESCP) prior to any land disturbance activities. What must an inspector verify during a stormwater management inspection? That the site is in compliance with the approved stormwater management plan, and that BMPs are functioning properly. What is the purpose of a Stormwater Pollution Prevention Plan (SWPPP)? To identify sources of pollution at a construction site and outline measures to prevent the contamination of stormwater runoff. 2 What is considered a Best Management Practice (BMP) for controlling stormwater runoff on a construction site? Installing silt fences and sediment basins to prevent sediment from being carried into nearby water bodies. When is a project required to apply for a General Permit for Stormwater Discharges in Virginia? When land-disturbing activities will disturb one acre or more of land. What is the function of a sediment basin on a construction site? To temporarily store stormwater runoff and allow sediment to settle before the water is discharged. What is the most effective way to reduce the amount of sediment leaving a construction site? By using sediment control practices such as silt fences, hay bales, and sediment basins. What is the primary role of the Virginia Department of Environmental Quality (DEQ) regarding stormwater management? To oversee and enforce compliance with stormwater regulations and provide guidance on best management practices. 3 What is required for the final stabilization of a construction site before the permit is closed? The site must have permanent vegetation, or an equivalent stabilization measure, to prevent erosion. What is an example of a structural BMP for stormwater management? A retention pond that captures and stores stormwater runoff to prevent flooding and water quality degradation. What is the significance of the Virginia Erosion and Sediment Control Law? It ensures that land-disturbing activities are properly controlled to minimize soil erosion and protect water quality. What is the minimum requirement for maintaining a stormwater management system on a construction site? The system must be inspected regularly, and any necessary maintenance must be performed to ensure its effectiveness. When should a Notice of Termination (NOT) be submitted for a construction project? 4 When all construction activities are complete, final stabilization is achieved, and all BMPs have been maintained. How often should stormwater management facilities be inspected during construction? At least once every 14 days and within 24 hours after a storm event of 0.5 inches or more. What is the purpose of the DEQ's Stormwater Management (SWM) Inspector Exam? To ensure that individuals have the knowledge and skills to effectively inspect and enforce stormwater management practices. What is one of the most important factors

Mostrar más Leer menos
Institución
VA DEQ SWM Inspector
Grado
VA DEQ SWM Inspector










Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
VA DEQ SWM Inspector
Grado
VA DEQ SWM Inspector

Información del documento

Subido en
9 de diciembre de 2024
Número de páginas
18
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

VA DEQ SWM Inspector Exam Questions
and Answers Graded A+
What is the purpose of the Virginia Stormwater Management Program (VSMP)?


✔✔To regulate and manage stormwater runoff from new and redevelopment projects to protect

water quality.




What is the minimum requirement for erosion and sediment control on construction sites under

Virginia law?


✔✔The site must have an approved Erosion and Sediment Control Plan (ESCP) prior to any land

disturbance activities.




What must an inspector verify during a stormwater management inspection?


✔✔That the site is in compliance with the approved stormwater management plan, and that

BMPs are functioning properly.




What is the purpose of a Stormwater Pollution Prevention Plan (SWPPP)?


✔✔To identify sources of pollution at a construction site and outline measures to prevent the

contamination of stormwater runoff.




1

,What is considered a Best Management Practice (BMP) for controlling stormwater runoff on a

construction site?


✔✔Installing silt fences and sediment basins to prevent sediment from being carried into nearby

water bodies.




When is a project required to apply for a General Permit for Stormwater Discharges in Virginia?


✔✔When land-disturbing activities will disturb one acre or more of land.




What is the function of a sediment basin on a construction site?


✔✔To temporarily store stormwater runoff and allow sediment to settle before the water is

discharged.




What is the most effective way to reduce the amount of sediment leaving a construction site?


✔✔By using sediment control practices such as silt fences, hay bales, and sediment basins.




What is the primary role of the Virginia Department of Environmental Quality (DEQ) regarding

stormwater management?


✔✔To oversee and enforce compliance with stormwater regulations and provide guidance on

best management practices.

2

, What is required for the final stabilization of a construction site before the permit is closed?


✔✔The site must have permanent vegetation, or an equivalent stabilization measure, to prevent

erosion.




What is an example of a structural BMP for stormwater management?


✔✔A retention pond that captures and stores stormwater runoff to prevent flooding and water

quality degradation.




What is the significance of the Virginia Erosion and Sediment Control Law?


✔✔It ensures that land-disturbing activities are properly controlled to minimize soil erosion and

protect water quality.




What is the minimum requirement for maintaining a stormwater management system on a

construction site?


✔✔The system must be inspected regularly, and any necessary maintenance must be performed

to ensure its effectiveness.




When should a Notice of Termination (NOT) be submitted for a construction project?


3
$9.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
BrilliantScores Chamberlain College Of Nursng
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
2819
Miembro desde
3 año
Número de seguidores
2233
Documentos
16100
Última venta
1 semana hace
latest updated documents, correct, verified & graded A study materials

get bundles, documents, test banks, case studies, shadow health's, ATIs, HESIs, study guides, summary, assignments & every kind of study materials.

3.8

774 reseñas

5
388
4
117
3
116
2
37
1
116

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes