100% de satisfacción garantizada Inmediatamente disponible después del pago Tanto en línea como en PDF No estas atado a nada 4.2 TrustPilot
logo-home
Examen

VA DEQ ESC Inspector Exam UPDATED ACTUAL Questions and CORRECT Answers

Puntuación
-
Vendido
-
Páginas
30
Grado
A+
Subido en
27-11-2024
Escrito en
2024/2025

VA DEQ ESC Inspector Exam UPDATED ACTUAL Questions and CORRECT Answers VESCP - CORRECT ANSWER- Virginia Erosion and Sediment Control Program - Administered by counties/cities (must), towns (may) - MUST BE APPROVED Minimum Standard 1 - CORRECT ANSWER- Stabilization

Mostrar más Leer menos
Institución
VA DEQ ESC Inspector
Grado
VA DEQ ESC Inspector










Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
VA DEQ ESC Inspector
Grado
VA DEQ ESC Inspector

Información del documento

Subido en
27 de noviembre de 2024
Número de páginas
30
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

VA DEQ ESC Inspector Exam UPDATED
ACTUAL Questions and CORRECT
Answers
VESCP - CORRECT ANSWER- Virginia Erosion and Sediment Control Program


- Administered by counties/cities (must), towns (may)
- MUST BE APPROVED


Minimum Standard 1 - CORRECT ANSWER- Stabilization


permanent or temporary soil stabilization shall be applied to denuded areas within seven days
after final grade is reached on any portion of the site; temporary soil stabilization shall be applied
within seven days to denuded areas that may not be at final grade but will remain dormant for
longer than 14 days; permanent stabilization shall be applied to areas that are to be left dormant
for more than one year


Site NOT at Final Grade - CORRECT ANSWER- - stabilize in 14 days
- temporarily seed
- mulch
- permanently stabilize if dormant > 1 year


Site at Final Grade - CORRECT ANSWER- - stabilize in 7 days (recommended
immediately)
- permanently or temporarily seed and mulch
- mulch/matting/straw


Minimum Standard 2 - CORRECT ANSWER- Stock Piles, Waste and Borrow Areas

,during construction, soil stock piles and borrow areas shall be stabilized or protected with
sediment trapping measures


mulch prevents erosion by protecting the surface from raindrop impact and silt fence intercepts
and detains from disturbed areas


Minimum Standard 3 - CORRECT ANSWER- Permanent Vegetation


permanent vegetation cover shall be established on denuded areas not otherwise permanently
stabilized (permanent vegetation shall not be considered established until a ground cover is
achieved that is uniform, mature enough to survive, and will inhibit erosion *there is no %
associated with this*)


reduce erosion and decrease sediment yield from disturbed area


this is the standard used to verify that a site is ready for release of bonds or surety


Minimum Standard 4 - CORRECT ANSWER- First-Step Measures


Sediment basins and traps, perimeter dikes, sediment barriers and other measures intended to
trap sediment shall be constructed as a first step in any land-disturbing activity and shall be made
functional before upslope land disturbance takes place


a certain amount of initial land disturbance may be required to provide access for equipment to
install the perimeter controls, but site clearing and grading should be kept to a minimum until the
perimeter controls are in place


intercepts and detains small amounts of sediment from disturbed areas during construction
operation to prevent sediment from leaving the site and decrease velocity of sheet flows and low-
to-moderate level channel flow

, Perimeter Controls - CORRECT ANSWER- assures that sediment does not leave the
perimeter of the land-disturbing area once site clearing, grading, and construction commences


Examples: silt fences, sediment traps, sediment basins, construction entrance, temporary
diversions, diversions


Minimum Standard 5 - CORRECT ANSWER- Earthen Structure Stabilization


stabilization measures shall be applied to earthen structures such as dams, dikes, and diversions
immediately after installation


reduce erosion and sedimentation and reduce damage from sediment and runoff to downstream
or off-site areas


Minimum Standard 6 - CORRECT ANSWER- Traps and Basins


sediment traps and basins shall be designed and constructed based upon the total drainage area
(not just disturbed area) to be served by the trap or basin


Sediment Traps - CORRECT ANSWER- minimum storage capacity shall be 134 cubic yards
per acre of drainage area and shall only control drainage areas less than 3 acres


*stone outlet = trap*


Sediment Basins - CORRECT ANSWER- surface runoff from disturbed areas that is
comprised of flow from drainage areas greater than or equal to 3 acres shall be controlled by a
basin; minimum storage capacity of a sediment basin shall be 134 cubic yards per acre of
drainage area; the outfall system shall, at a minimum, maintain the structural integrity of the
basin during a 25-year storm of 24-hour duration; runoff coefficients used in runoff calculations
shall correspond to a bare earth condition or those conditions expected to exist while the
sediment basin is utilized.
$10.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada


Documento también disponible en un lote

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
MGRADES Stanford University
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
1091
Miembro desde
1 año
Número de seguidores
102
Documentos
68972
Última venta
2 horas hace
MGRADES (Stanford Top Brains)

Welcome to MGRADES Exams, practices and Study materials Just think of me as the plug you will refer to your friends Me and my team will always make sure you get the best value from the exams markets. I offer the best study and exam materials for a wide range of courses and units. Make your study sessions more efficient and effective. Dive in and discover all you need to excel in your academic journey!

3.8

175 reseñas

5
75
4
31
3
46
2
8
1
15

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes