A defined portion of the work that is priced separately is:
A. A Unit Cost.
B. Lump Sum.
C. Alternate. - ANSWER-C
A key factor affecting project delivery
A. Complexity.
B. Time.
C. Cost.
D. Quality. - ANSWER-B
A particular material may be indicated several times on the drawings but is specified in
how many locations:
A. One.
B. Two.
C. According to the number of trades involved.
D. As determined by Division 01. - ANSWER-A
A subcontractor is obligated to the prime contractor in the same manner as the prime
contractor is obligated to the:
A. Architect
B. Owner
C. Material Supplier
D. Principal in Charge - ANSWER-B
A Unit Price is:
A. A cost determined by the A/E.
B. Amount determined by number of units multiplied by a unit cost in the Agreement.
C. A cost listed on the Bid Form. - ANSWER-B
Addenda are used to:
A. Modify the procurement documents before award of the contract.
B. Modify the contract documents after award of the contract.
C. Modify drawings and specifications only.
D. Formalize verbal instructions given during bidding. - ANSWER-A
Administrative and procedural requirements are specified in:
A. General Conditions.
B. Supplementary Conditions.
C. Division 01 General Requirements.
D. Bidding requirements.
, E. Instructions to Bidders. - ANSWER-C
An Allowance is included in the base bid for:
A. Cost of an item to be selected.
B. Time to extend the work.
C. Includes both time and costs of an item. - ANSWER-C
An Alternate:
A. Is the same as an option in the specifications.
B. Is used for the same purpose as unit prices.
C. Should be described in Division 01 and specified in the appropriate specification
sections.
D. Should be described in detail on the bid form. - ANSWER-C
Before a model building code can become the building code for a jurisdiction, it has to
be adopted by?
A. Authority Having Jurisdiction
B. State Government
C. Building Inspector
D. International Organization for Standardization - ANSWER-A
Contract Documents consist of:
A. Agreement between Owner and Contractor, Conditions of the Contract, Drawings,
and Specifications, Addenda and Modifications, other Documents listed in the
Agreement.
B. Agreement between Owner and Contractor, Conditions of the Contract, Drawings
and Specifications, Project Manual, Shop Drawings.
C. Agreement between Owner and Contractor, Conditions of the Contract, Drawings
and Specifications, Instructions to Bidders, Bid Form, Addenda, Modifications, other
documents listed in the Agreement. - ANSWER-A
Contract documents include:
A. Written portions of the contract only.
B. Graphic portions of the contract only.
C. Both written and graphic portions of the contract.
D. Invitation to Bid. - ANSWER-C
Defined as the written and graphic documents prepared or assembled by the A/E for
communicating the project design for construction and administering the construction
contract:
A. Construction Documents
B. Plans
C. Procurement Documents
D. Conditions of the Contract - ANSWER-A