Construction FE Civil Exam Questions with 100% Verified Correct Answers Is the most traditional project delivery method and appeals to those looking for low-cost bids. In this method, the owner contracts designers and builders separately. - Correct Answer Design-bid-build is a construction project delivery method where the designer and builder work together under a single contract from the beginning of the project in order to ensure unity and collaboration throughout the process. - Correct Answer Design- build Select all that clearly demonstrate an advantage of the Design-Build project delivery over the Design-Bid-Build approach: - There is single point of contractual responsibility for the owner for the entire project -There are contractual relationships with the Owner that prevent a conflict of interest -The design is clearly and explicitly defined at the outset of the project - The design includes significant collaboration between the Engineer and the Contractor -The schedule can be fast-tracked and construction can begin before the complete project design is finalized - The Owner will receive a project at the lowest competitive cost - Correct Answer There is single point of contractual responsibility for the owner for the entire project There is single point of contractual responsibility for the owner for the entire project The schedule can be fast-tracked and construction can begin before the complete project design is finalized An indemnification clause in an engineer's design contract is typically tied to: A. Negligent engineering design B. Claims submitted by parties affected by a failure C. Project cost overruns D. Improper construction methods by the Contractor - Correct Answer A. Negligent engineering design Collusion on a construction project typically refers to which of the following?

Mostrar más Leer menos
Institución
Construction FE Civil
Grado
Construction FE Civil








Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
Construction FE Civil
Grado
Construction FE Civil

Información del documento

Subido en
12 de noviembre de 2024
Número de páginas
2
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

Construction FE Civil Exam Questions with 100% Verified
Correct Answers
Which of the following duties would normally NOT be a responsibility of the estimating
department within a general contractor's organization?

(A) obtaining bid documents
(B) securing subcontractor/material quotations
(C) project cost accounting
(D) delivering competitive or negotiated proposals - answers (C) project cost
accounting

In competitive bidding, when the bids are all opened, the owner will normally award the
contract to the lowest

(A) available bidder
(B) qualified bidder
(C) responsible bidder
(D) bonded bidder - answers (C) responsible bidder

The term "design build" means the

(A) design firm designs the project & the client builds it
(B) design firm both designs & builds the project
(C) client designs the project & the contractor builds it
(D) contractor designs the project & the subcontractors
build it - answers (B) design firm both designs & builds the project

An activity is coded as 0793-31 62 13.16 using the Construction Specifications
Institute's MasterFormat 2012. THis coding represents

(A) clearing and grubbing land
(B) demolition of an existing structure
(C) shoring an excavation
(D) driving a deep foundation pile - answers (D) driving a deep foundation pile

Which of the following organizations is NOT a contributor to the standard design and
construction contract documents developed by the Engineers Joint Contract Documents
Committee (EJCDC)?

(A) National Society of Professional Engineers
(B) Construction Specifications Institute
(C) Associated General Contractors of America
(D) American Institute of Architects - answers (D) American Institute of Architects

What factor is responsible for an increase in production rates as a new task is repeated
and practiced?
$16.49
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
oassignment Chamberlain College Nursing
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
140
Miembro desde
5 año
Número de seguidores
137
Documentos
1619
Última venta
3 meses hace
Homework Help, Study Guide

I am multidisciplinary specializing in offering help in a range of subjects. My main focus is to equip learners at all levels with the relevant knowledge to enable them to realize their full potential. I do take pride in our high-quality services and i am always ready to support all clients.

3.5

26 reseñas

5
12
4
2
3
5
2
0
1
7

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes