In project documents order, which Document(s) has higher authority than the
Supplemental Specifications?
A. Standard Specifications
B. Plans
C. Technical Special Provisions
D. All of the above
E. Both B and C - ANSWERS-(E. Both B and C) Plans and Technical Special
Provisions
What is the desired tack coat application rate for a milled surface?
A. 0.02-0.08 gal/yd²
B. 0.45 gal/yd²
C. 0.06 gal/yd²
D. 0.08 gal/yd²
E. All the above - ANSWERS-(C.) 0.06 gal/yd²
Density Testing for acceptance will not be performed on:
A. Shoulder less than 5 feet or less
B. Miscellaneous Asphalt Pavement
C. Cross-overs and intersections less than 1000 feet
, D. Acceleration and deceleration lanes less than 1000 feet
E. All the above - ANSWERS-(E. All the Above) - Shoulder less than 5 feet or less,
Miscellaneous Asphalt Pavement, Cross-overs and intersections less than 1000
feet, and Acceleration and deceleration lanes less than 1000 feet
A _______ is utilized when attempting to match elevations of two mats placed
side by side - ANSWERS-(D.) Joint Matcher
Experts maintain that 95% of paver related problems can be eliminated by:
A. Keeping the hopper empty between loads
B. Keeping the paver running slow
C. Adjusting the tow points constantly
D. Maintaining a uniform head of material in front of the auger
E. All the above - ANSWERS-(D.) Maintaining a uniform head of material in front
of the auger
When milling for slope on the mainline roadway, if the average of 10 slope checks
for the VT differs from the target by 0.1% what is required? - ANSWERS-(A.) Tell
Contractor to shut down milling operation. Make corrections
The cores taken for Independent Verification (IV) must:
A. Be from the same location as the QC cores
B. Be from the same LOT and Sublots as the IV plant samples
C. Meet the requirements of Table 334-5 (master production)