DBIA - Project Delivery - True or False
Questions and Answers
Twentieth Century Public contracting laws in North America have historically mandated professional
design services be purchased separated from the selection of contractors solely on the basis of lowest
responsible bid. T or F? - ANSWER✔✔-True
Most Public Procurement statutes require the selection of design services be purchased on the basis of
lowest responsible bid? T/F? - ANSWER✔✔-False
There are always at least three parties involved in every project delivery process; the Owner, Architect
and Contractor. T/F? - ANSWER✔✔-True
It is recommended to get a contractor on board early during the business and planning stage of a DB
project to have the best opportunity to achieve all objectives. T/F - ANSWER✔✔-True
The primary goal in choosing a delivery method is to ensure that it will meet the Owner's project
objectives while at the same time allowing the project to be completed on time and within budget? T/F -
ANSWER✔✔-True