DBIA - Project Delivery Exam Practice Questions and Answers The existing federal law that required federal projects exceeding 100k to require both a performance and a payment bond. Created a legal separation between construction & Design - ANSWER-Miller Act What are 3 fundamental decisions an Owner must make when initiating a feasible project? - ANSWER-Delivery system, Type of Procurement and Type of Contract Format. What is the most common project delivery system? - ANSWER-Design Bid Build (Low Bid) In traditional DBB delivery, who does the architect sign their contract with? - ANSWER-The Owner What type of relationship does the contractor have with an architect in Design Bid Build? - ANSWER- None Why would you choose a Design Build delivery System? - ANSWER-Scheduling Restraints or needs to be fast-tracked If the owner wants to shift risk to one party, what project delivery method would they choose? - ANSWER-Design Build ©EMILLECT 2024/2025 ACADEMIC YEAR. ALL RIGHTS RESERVED FIRST PUBLISH OCTOBER 2024 Page 2/7 What type of project delivery best suits a complex project requiring close coordination of design and construction expertise? - ANSWER-Design Build What are some forms of Design Build entities? - ANSWER-1 - Joint Venture 2 - Integrated DB Firm 3- A/E Led 4 - Contractor Led Does the Owner bear risk in a design-bid-build? - ANSWER-Yes What are some reasons owners choose DBB? - ANSWER-1 - Linear project delivery 2 - Well defined and familiar relationships 3 - Benefit of Open Market Competition 4 - Owner is actively involved in design until documents are 100% complete 1 - Owner wants absolute design control 2 - The programming limits flexibility and innovation 3 - The Owner cannot provide programming and performance requirements. - ANSWER-Limiting Factors to Design Build ©EMILLECT 2024/2025 ACADEMIC YEAR. ALL RIGHTS RESERVED FIRST PUBLISH OCTOBER 2024 Page 3/7 The most common DB entity structural arrangement? - ANSWER-Contractor Led What contracts does the owner holds in a CM @ Risk delivery method. - ANSWER-1 - Contractor 2 - Architect How architect/engineering firms are typically selected? - ANSWER-Qualifications and Best Price A procurement option where the DB'er is selected strictly on the basis of predetermined values and qualification criteria already determined in consideration of reputation of prior dealings with the owner? Often highly specialized. - ANSWER-Sole Source/Direct Selection The procurement option generally used for a CM @ Risk project delivery system: - ANSWER- Qualifications Based Selection Type of Procurement that considers: qualifications, price and technical desi

Mostrar más Leer menos
Institución
DBIA
Grado
DBIA









Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
DBIA
Grado
DBIA

Información del documento

Subido en
30 de octubre de 2024
Número de páginas
7
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

©EMILLECT 2024/2025 ACADEMIC YEAR. ALL RIGHTS RESERVED

FIRST PUBLISH OCTOBER 2024




DBIA - Project Delivery Exam Practice

Questions and Answers


The existing federal law that required federal projects exceeding 100k to require both a performance

and a payment bond. Created a legal separation between construction & Design - ANSWER✔✔-Miller

Act


What are 3 fundamental decisions an Owner must make when initiating a feasible project? -

ANSWER✔✔-Delivery system, Type of Procurement and Type of Contract Format.


What is the most common project delivery system? - ANSWER✔✔-Design Bid Build (Low Bid)


In traditional DBB delivery, who does the architect sign their contract with? - ANSWER✔✔-The Owner


What type of relationship does the contractor have with an architect in Design Bid Build? - ANSWER✔✔-

None


Why would you choose a Design Build delivery System? - ANSWER✔✔-Scheduling Restraints or needs to

be fast-tracked


If the owner wants to shift risk to one party, what project delivery method would they choose? -

ANSWER✔✔-Design Build

Page 1/7

, ©EMILLECT 2024/2025 ACADEMIC YEAR. ALL RIGHTS RESERVED

FIRST PUBLISH OCTOBER 2024




What type of project delivery best suits a complex project requiring close coordination of design and

construction expertise? - ANSWER✔✔-Design Build


What are some forms of Design Build entities? - ANSWER✔✔-1 - Joint Venture


2 - Integrated DB Firm


3- A/E Led


4 - Contractor Led


Does the Owner bear risk in a design-bid-build? - ANSWER✔✔-Yes


What are some reasons owners choose DBB? - ANSWER✔✔-1 - Linear project delivery


2 - Well defined and familiar relationships


3 - Benefit of Open Market Competition


4 - Owner is actively involved in design until documents are 100% complete


1 - Owner wants absolute design control


2 - The programming limits flexibility and innovation


3 - The Owner cannot provide programming and performance requirements. - ANSWER✔✔-Limiting

Factors to Design Build


Page 2/7
$11.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada


Documento también disponible en un lote

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Emillect West Virginia University
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
28
Miembro desde
1 año
Número de seguidores
2
Documentos
3004
Última venta
2 meses hace
GOLDEN ORCHIDS STORE.

On this page, you find all documents, package deals, and flashcards offered by seller Emillect.

3.0

4 reseñas

5
1
4
0
3
2
2
0
1
1

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes