Which of the following statements is NOT true? a. The government encourages the maximum practicable commercial use of inventions made under government contracts. b. The government recognizes rights in data developed at private expense, and limits its demands for delivery of that data. c. The government requires that contractors obtain permission from copyright owners before including copyrighted works, owned by others, in data to be delivered to the government. d. Generally, the government will refuse to award a contract on the grounds that the prospective contractor may infringe a patent. - ANSWERd. Generally, the government will refuse to award a contract on the grounds that the prospective contractor may infringe a patent. FAR 27.102 Performance and payment bonds are required or may be required for a. construction contracts and services and supply contracts exceeding $2,000. b. construction contracts exceeding $150,000. c. any contract for services, d. construction contracts exceeding $150,000 and services and supply contracts exceeding the SAT when necessary to protect the governments interests. - ANSWERd. construction contracts exceeding $150,000 and services and supply contracts exceeding the SAT when necessary to protect the governments interests. FAR 28.102-1(a), 28.103-1(a), 28.103-2(a) Cost Accounting Standards Board rules and regulations apply to a. negotiated contracts and subcontracts. b. sealed bid contracts. c. contracts with small business concerns. d. bridge contracts. - ANSWERa. negotiated contracts and subcontracts. FAR 30.201-5 Which of the following statements about advance agreements is NOT true? a. Advance agreements may only be negotiated with a particular contractor for a single contract. b. Advance agreements may be negotiated either before or during a contract. c. The agreement must be in writing. d. The agreements must be incorporated into applicable current and future contracts. - ANSWERa. Advance agreements may only be negotiated with a particular contractor for a single contract. FAR 31.109 A cost is reasonable if, in its nature and amount, it does not exceed that which would be a. incurred by a prudent person in the conduct of competitive business. b. accrued by a prudent person in the conduct of competitive business. c. determined to be allowable by the CO. d. determined to be allocable by the CO. - ANSWERa. incurred by a prudent person in the conduct of competitive business. FAR 31.201-3 What definition best describes alternative dispute resolution? a. Procedures used to resolve issues in controversy. b. Procedures voluntarily used to resolve issues in controversy. c. Procedures used for asserting and resolving claims. d. Procedures voluntarily used for asserting and resolving claims. - ANSWERb. Procedures voluntarily used to resolve issues in controversy. FAR 33.214 The government's policy is to try to resolve all contractual issues in controversy by a. mutual agreement at the CO's level. b. bilateral agreement at the CO's level. c. mutual agreement at a level above the CO. d. unilateral agreement at the CO's level. - ANSWERa. mutual agreement at the CO's level. FAR 33.204 After receiving the GAO's written notice that a protest has been filed, an agency must give notice a. of the protest to the contractor or all parties who appear to have a reasonable prospect of receiving an award. b. of the protest only to the prime contractor performing the work. c. of the protest to all parties who appear to have a reasonable prospect of receiving award and begin compiling the information necessary to report to the GAO. d. through a government-wide point of entry (GPE). - ANSWERa. of the protest to the contractor or all parties who appear to have a reasonable prospect of receiving an award. FAR 33.104 Does a $75,000 claim resulting from a reduction of $350,000 and an increase of $275,000 require certification? a. No, because the claimed amount is less than $100,000. b. Yes, because the aggregate value of the claim exceeds $100,000. c. No, because the claimed amount is less than $500,000. d. Yes, because the aggregate value of the claim exceeds $500,000. - ANSWERb. Yes, because the aggregate value of the claim exceeds $100,000. FAR 33.207(d) Protests may be filed with a. either the agency or the GAO. b. the agency, the GAO, or the U.S. Court of Claims. c. either the contracting officer or the U.S. Court of Federal Claims. d. Small Claims Court for awards under the SAT. - ANSWERb. the agency, the GAO, or the U.S. Court of Claims. FAR 33.102

Mostrar más Leer menos
Institución
CFCM Stu
Grado
CFCM Stu

Vista previa del contenido

CFCM Study Guide: FULL TEST QUESTIONS &
ANSWERS(GRADED A+)


Which of the following statements is NOT true?



a. The government encourages the maximum practicable commercial use of inventions made under
government contracts.

b. The government recognizes rights in data developed at private expense, and limits its demands for
delivery of that data.

c. The government requires that contractors obtain permission from copyright owners before
including copyrighted works, owned by others, in data to be delivered to the government.

d. Generally, the government will refuse to award a contract on the grounds that the prospective
contractor may infringe a patent. - ANSWERd. Generally, the government will refuse to award a
contract on the grounds that the prospective contractor may infringe a patent.



FAR 27.102



Performance and payment bonds are required or may be required for



a. construction contracts and services and supply contracts exceeding $2,000.

b. construction contracts exceeding $150,000.

c. any contract for services,

d. construction contracts exceeding $150,000 and services and supply contracts exceeding the SAT
when necessary to protect the governments interests. - ANSWERd. construction contracts exceeding
$150,000 and services and supply contracts exceeding the SAT when necessary to protect the
governments interests.



FAR 28.102-1(a), 28.103-1(a), 28.103-2(a)



Cost Accounting Standards Board rules and regulations apply to



a. negotiated contracts and subcontracts.

,b. sealed bid contracts.

c. contracts with small business concerns.

d. bridge contracts. - ANSWERa. negotiated contracts and subcontracts.



FAR 30.201-5



Which of the following statements about advance agreements is NOT true?



a. Advance agreements may only be negotiated with a particular contractor for a single contract.

b. Advance agreements may be negotiated either before or during a contract.

c. The agreement must be in writing.

d. The agreements must be incorporated into applicable current and future contracts. - ANSWERa.
Advance agreements may only be negotiated with a particular contractor for a single contract.



FAR 31.109



A cost is reasonable if, in its nature and amount, it does not exceed that which would be



a. incurred by a prudent person in the conduct of competitive business.

b. accrued by a prudent person in the conduct of competitive business.

c. determined to be allowable by the CO.

d. determined to be allocable by the CO. - ANSWERa. incurred by a prudent person in the conduct of
competitive business.



FAR 31.201-3



What definition best describes alternative dispute resolution?



a. Procedures used to resolve issues in controversy.

b. Procedures voluntarily used to resolve issues in controversy.

c. Procedures used for asserting and resolving claims.

,d. Procedures voluntarily used for asserting and resolving claims. - ANSWERb. Procedures voluntarily
used to resolve issues in controversy.



FAR 33.214



The government's policy is to try to resolve all contractual issues in controversy by



a. mutual agreement at the CO's level.

b. bilateral agreement at the CO's level.

c. mutual agreement at a level above the CO.

d. unilateral agreement at the CO's level. - ANSWERa. mutual agreement at the CO's level.



FAR 33.204



After receiving the GAO's written notice that a protest has been filed, an agency must give notice



a. of the protest to the contractor or all parties who appear to have a reasonable prospect of
receiving an award.

b. of the protest only to the prime contractor performing the work.

c. of the protest to all parties who appear to have a reasonable prospect of receiving award and
begin compiling the information necessary to report to the GAO.

d. through a government-wide point of entry (GPE). - ANSWERa. of the protest to the contractor or
all parties who appear to have a reasonable prospect of receiving an award.



FAR 33.104



Does a $75,000 claim resulting from a reduction of $350,000 and an increase of $275,000 require
certification?



a. No, because the claimed amount is less than $100,000.

b. Yes, because the aggregate value of the claim exceeds $100,000.

c. No, because the claimed amount is less than $500,000.

, d. Yes, because the aggregate value of the claim exceeds $500,000. - ANSWERb. Yes, because the
aggregate value of the claim exceeds $100,000.



FAR 33.207(d)



Protests may be filed with



a. either the agency or the GAO.

b. the agency, the GAO, or the U.S. Court of Claims.

c. either the contracting officer or the U.S. Court of Federal Claims.

d. Small Claims Court for awards under the SAT. - ANSWERb. the agency, the GAO, or the U.S. Court
of Claims.



FAR 33.102



Who can authorize continued performance in the face of a protest after award?



a. the chief of the contracting office

b. the CO, provided his findings are documented in the file.

c. the head of the contracting activity.

d. the commanding officers. - ANSWERc. the head of the contracting activity.



FAR 33.104(c)(2)



The CO shall consider all protests and seek legal advice



a. only if protests are received after award and filed directly with the agency.

b. only if the protest is received after award and filed directly with the GAO.

c. whether protests are submitted before or after award.

d. whether protests are submitted before or after award and whether filed directly with the GAO, the
U.S Court of Claims, or the agency. - ANSWERd. whether protests are submitted before or after
award and whether filed directly with the GAO, the U.S Court of Claims, or the agency.

Escuela, estudio y materia

Institución
CFCM Stu
Grado
CFCM Stu

Información del documento

Subido en
8 de octubre de 2024
Número de páginas
51
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

$14.49
Accede al documento completo:

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
ClassRep2 Strayer University
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
68
Miembro desde
3 año
Número de seguidores
46
Documentos
2177
Última venta
1 semana hace

2.1

7 reseñas

5
1
4
1
3
0
2
1
1
4

Documentos populares

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes