critical chain method - ANSWER a schedule network analysis technique that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties resource leveling - ANSWER a resource optimization technique expectancy theory (also called Vroom's expectancy theory) - ANSWER theory that says employees' efforts will lead to effective performance and the employees will be rewarded for accomplishments Earned value management - ANSWER methodology that combines scope, schedule, and resource measurements to assess project performance and progress

Mostrar más Leer menos
Institución
PMP
Grado
PMP









Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
PMP
Grado
PMP

Información del documento

Subido en
7 de octubre de 2024
Número de páginas
6
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

PMP Exam Prep Vocabulary|| 55
QUESTIONS & CORRECT
SOLUTIONS(GRADED A)
critical chain method - ANSWER a schedule network analysis technique that allows the project team to
place buffers on any project schedule path to account for limited resources and project uncertainties



resource leveling - ANSWER a resource optimization technique



expectancy theory (also called Vroom's expectancy theory) - ANSWER theory that says employees'
efforts will lead to effective performance and the employees will be rewarded for accomplishments



Earned value management - ANSWER methodology that combines scope, schedule, and resource
measurements to assess project performance and progress



analogous estimating - ANSWER uses top-down estimating techniques



joint application design - ANSWER a type of facilitated workshop used in the software development
industry to bring business subject matter experts and the development team together to improve the
software development process



corrective action - ANSWER intentional activity that realigns the performance of the project work with
the project management plan



preventive action - ANSWER intentional activity that ensures future performance of project work is
aligned with project management plan



defect repair - ANSWER intentional activity to modify a nonconforming product or product component

, change request - ANSWER formal proposal to modify any document, deliverable, or baseline; may
include corrective action, preventive action, defect repair, and updates



product scope - ANSWER requirements that relate to product of project



project scope - ANSWER work project will do to deliver product of project; it encompasses product scope




decentralized contracting - ANSWER an environment where the project manager is assigned to one
project full-time and reports to the project manager



default letter - ANSWER letter is used to provide written notice to a person or organization that is in
default or breach of contract. That is, they have failed to meet the

obligations required in the contract.



performance reporting - ANSWER pulling together info from work performance reports and
communicating it with the appropriate stakeholders (under Manage Communications process)



scope verification - ANSWER process of formalizing acceptance of the project scope by the stakeholders.
It requires reviewing work products and results to ensure that all were completed correctly and
satisfactorily.



procurement statement of work (SOW) - ANSWER work to be done on each procurement that must be
as clear, complete, and concise as possible and include ALL work and activities seller is required to
complete; made in the Plan Procurement Management process



procurement management plan - ANSWER document which shows how procurements will be planned,
executed, controlled, and closed for the project; part of Plan Procurement Management process



fixed price (FP) contract - ANSWER contract where the goods, products, or services have well-defined
specs or requirements.
$9.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada


Documento también disponible en un lote

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Lecchris West Virgina University
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
40
Miembro desde
2 año
Número de seguidores
15
Documentos
3203
Última venta
1 mes hace
LECCHRIS

3.8

6 reseñas

5
2
4
1
3
3
2
0
1
0

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes