Certain key stakeholders are dissatisfied with the development of a key feature of a project. They express their dissatisfaction during an iteration review meeting. What should the project manager do first to resolve this issue? -Identify the reasons why there are issues with the feature, then address the issue. -Gather the project team for a brainstorming session and identify a solution. -Create a list of the pros and cons of the situation to define the impact of the conflict. -Add a neutral party, such as the project sponsor, to function as a negotiator with stakeholders. - ANSWER -Identify the reasons why there are issues with the feature, then address the issue. Working with the customer in identifying the source of dissatisfaction with the feature is a good first step. This also helps with resolving conflict between the team and stakeholders.

Mostrar más Leer menos
Institución
PMP
Grado
PMP










Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
PMP
Grado
PMP

Información del documento

Subido en
7 de octubre de 2024
Número de páginas
29
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

PMP Exam Prep|| 60 QUESTIONS ||
CORRECT SOLUTIONS
Certain key stakeholders are dissatisfied with the development of a key feature of a project. They express
their dissatisfaction during an iteration review meeting. What should the project manager do first to
resolve this issue?



-Identify the reasons why there are issues with the feature, then address the issue.

-Gather the project team for a brainstorming session and identify a solution.

-Create a list of the pros and cons of the situation to define the impact of the conflict.

-Add a neutral party, such as the project sponsor, to function as a negotiator with stakeholders. -
ANSWER -Identify the reasons why there are issues with the feature, then address the issue.



Working with the customer in identifying the source of dissatisfaction with the feature is a good first
step. This also helps with resolving conflict between the team and stakeholders.



A project team is comprised of local and virtual team members. To manage scheduling priority conflicts
among team members, the project manager schedules a video conference call. Which conflict resolution
technique does this statement demonstrate?



Force/Direct

Smooth/Accommodate

Compromise/Reconcile

Collaborate/Problem Solve - ANSWER Collaborate/Problem Solve



The collaborate/problem solve approach incorporates multiple viewpoints and insights from differing
perspectives. It requires a cooperative attitude and open dialogue that typically leads to consensus and
commitment. This approach can result in a win-win situation.



A Project Manager joins a project as a replacement on a project team. During initial meetings, the
Project Manager realized there are many differing opinions about how to address technical decisions.

, Team members did not respect each other's ideas, and the environment was becoming
counterproductive. However, now the team has begun to communicate more effectively and develop
some processes and procedures for working together. In what phase of development is the team now?



-Performing

-Norming

-Storming

-Forming - ANSWER Norming



Storming often starts where there is a conflict between team members' natural working styles. People
may work in different ways for all sorts of reasons but, if differing working styles cause unforeseen
problems, they may become frustrated and counterproductive. Once the team members start working
together and adjusting their work habits and behaviors to be more supportive, the team has transitioned
into Norming.



A project manager joins a project team, replacing a manager who left. During initial meetings, the
project manager realized that the team members have differing opinions about how to address technical
decisions. Team members did NOT respect each other's ideas, and the environment was becoming
counterproductive. However, now with the new manager's leadership, the team has begun to
communicate more effectively and develop some processes and procedures for working together.In what
phase of development is the team now?



-Performing

-Norming

-Storming

-Forming - ANSWER Norming



During the norming phase, team members begin to work together and adjust their work habits and
behaviors to support the team. The team members learn to trust each other.



A project is comprised of three highly dependent parts, each being completed by its own project team.
The team leader, worried that conflicts might arise when the outputs from the three teams are
combined, asks for advice.What advice should the project manager provide?

, - Decide which team's work should be prioritized, then delay the work from the other two teams to
ensure there are NO conflicts.

-Identify potential conflicts and then arrange for a weekly joint meeting with the members of the three
teams to review each other's work.

-Continue to let all three teams work simultaneously, recognizing that conflicts can be addressed at the
testing phase.

-Document conflicts as they occur and take action to remedy any problems that arise. - ANSWER Identify
potential conflicts and then arrange for a weekly joint meeting with the members of the three teams to
review each other's work.



Consistent communication is important for ensuring a lower probability of issues and successfully
addressing existing risks.



.



Conflict should be addressed in private first, to better understand the concern being raised. Exploring the
concern after the meeting gives the project manager an opportunity to verify the concern and determine
needed next steps without disrupting a large meeting.



A product owner repeatedly complains, saying that a function developed by the development team does
NOT seem to align with the original design. What will help to solve this issue?



-Ask the development team to rewrite the function so that it matches with the project scope.

-Update the product owner twice per week on product development.

-Ask the product owner to explain his point of view clearly to the team.

-Ask the quality assurance team to identify any mismatches in functionality compared to the initial
design. - ANSWER Update the product owner twice per week on product development.



The product owner has already explained the requirements in the original design. The solution here is to
keep the product owner updated on development so that the team can adjust their work if it goes out of
scope.
$12.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada


Documento también disponible en un lote

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Lecchris West Virgina University
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
40
Miembro desde
2 año
Número de seguidores
15
Documentos
3203
Última venta
1 mes hace
LECCHRIS

3.8

6 reseñas

5
2
4
1
3
3
2
0
1
0

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes