CEE 4100 Exam 1 Questions and Correct Solutions
CEE 4100 Exam 1 Questions and Correct Solutions Activity Labor Cost - CORRECT ANSWER-duration x hourly crew labor cost Advertisement for construction - CORRECT ANSWER-request for eligibility to bid - right to reject bids Architect/Engineer - CORRECT ANSWER-•professional that designs project. Usually direct employee of owner by contract Bid Bond - CORRECT ANSWER-Ensures bidder stays with the project Bid Solicitation or Advertisement for Bid - CORRECT ANSWER-contains information regarding bidding documents for public projects BIDDING DOCUMENTS VS. CONTRACT DOCUMENTS - CORRECT ANSWER-Both. agreement, bid form, addenda, drawings, general/supplementary conditions, technical specs Bid docs: notice/invitation to bidders, instruction to bidder, bid bond, performance bond, payment bond Contract docs: modifications business organization - CORRECT ANSWER-I. start of business (fundamental purpose, scope, action plan) 2. design organizational structure (authority, responsibility/ delegation) Civil engineering Specialties - CORRECT ANSWER-ENVIRONMENTAL AND WATER RESOURCES GEOTECHNICAL SYSTEMS STRUCTURAL SYSTEMS
Escuela, estudio y materia
- Institución
- CEE 4100
- Grado
- CEE 4100
Información del documento
- Subido en
- 29 de septiembre de 2024
- Número de páginas
- 9
- Escrito en
- 2024/2025
- Tipo
- Examen
- Contiene
- Preguntas y respuestas
Temas
-
cee 4100 exam 1 questions and correct solutions
-
correct solutions activity labor cost
Documento también disponible en un lote