Unit 4 Boiler Operation Exam Questions And Answers 100% Correct

Puntuación
-
Vendido
-
Páginas
5
Grado
A+
Subido en
27-09-2024
Escrito en
2024/2025

Unit 4 Boiler Operation Exam Questions And Answers 100% CorrectUnit 4 Boiler Operation Exam Questions And Answers 100% CorrectUnit 4 Boiler Operation Exam Questions And Answers 100% CorrectUnit 4 Boiler Operation Exam Questions And Answers 100% Correct When should wet layup be used? Select one: a. When a boiler may be exposed to freezing conditions. b. When a boiler is on standby. c. For long term storage. d. When desiccant is unavailable. - ANSWER-b In a multiple boiler high pressure steam plant, when starting an entire system from cold Select one:

Mostrar más Leer menos
Institución
Unit 4 Boiler Operation
Grado
Unit 4 Boiler Operation









Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
Unit 4 Boiler Operation
Grado
Unit 4 Boiler Operation

Información del documento

Subido en
27 de septiembre de 2024
Número de páginas
5
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

Unit 4 Boiler Operation Exam
Questions And Answers 100%
Correct
When should wet layup be used?
Select one:
a. When a boiler may be exposed to freezing conditions.
b. When a boiler is on standby.
c. For long term storage.
d. When desiccant is unavailable. - ANSWER-b


In a multiple boiler high pressure steam plant, when starting an entire system from
cold
Select one:
a. A small auxiliary heating boiler is used to warm the steam lines while the power
boilers are warming.
b. All the boilers are started and warmed at the same time.
c. The entire system warms and pressurizes as one boiler warms, except for the
boilers being left off line.
d. Boilers remaining off-line must have their boiler and header stop valves open,
and their non-return drain valves shut. - ANSWER-c


Although boilers have many different ignition systems, they all follow the same
sequence of steps. Which of the following is the third step?
Select one:
a. Main burner ignition
b. Pilot ignition
c. Post Purge
d. Pre-purge - ANSWER-a

, How often should the low water cut-off of a low pressure steam heating boiler be
blown off?
Select one:
a. Daily
b. Monthly
c. Twice per shift
d. Weekly - ANSWER-a


Deaerators often have low-level alarms and low-low level trips
Select one:
a. in case the boiler trips.
b. in case the boiler feedwater pumps trip.
c. in case the boiler feedwater valve fails open.
d. in case the condensate transfer pumps trip. - ANSWER-d


A well-planned PM system will
Select one:
a. ensure equipment longevity.
b. create less need for rounds and inspections.
c. will cover only the most critical plant equipment.
d. respond quickly to equipment breakdown. - ANSWER-a


When preparing to start a steam boiler with a fully modulating firing rate control,
set the manual-automatic switch to _________ and the flame control switch to the
__________ position.
Select one:
a. automatic, low-fire
b. manual, low-fire
c. manual, high-fire
d. manual, automatic - ANSWER-b
$12.49
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada


Documento también disponible en un lote

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
NursingTutor1 West Virginia University
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
1633
Miembro desde
2 año
Número de seguidores
1073
Documentos
18045
Última venta
2 días hace
Nursing Tutor

Paper Due? Worry not. Hello. Welcome to NursingTutor. Here you\'ll find verified study materials for your assignments, exams and general school work. All papers here are graded A to help you get the best grade. Also, I am a friendly person so, do not hesitate to send a message in case you have a query. I wish you Luck.

3.9

447 reseñas

5
212
4
76
3
89
2
21
1
49

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes