Consider the following project.
Compute the slack time for activity C.
0
4
2
3
Question 2
A PERT/CPM activity has an optimistic time estimate of 3 days, a most likely time estimate of 8 days,
and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is:
7.0
,7.5
, 8.0
8.5
Question 3
A PERT/CPM activity has an optimistic time estimate of 3 days, a most likely time estimate of 8 days,
and a pessimistic time estimate of 10 days. The standard deviation of this activity is:
7/9
7/6
1/3
2/3
Question 4
A dummy activity in a PERT network allows us to
specify the positive time and resources required to complete the
activity. maintain the precedence relationships.
add more starting
nodes. add more
ending nodes.