CGM-C UPDATED Actual Exam Questions and CORRECT Answers The purpose of Construction Quality Management is to: - CORRECT ANSWER- Achieve the quality established by properly developed requirements through the combined responsibility, but separate, efforts of contractor and Government personnel Construction Quality Management is the performance of tasks, which ensure that design and construction is performed: - CORRECT ANSWER- According to plans and specifications, on time, within a defined budget and a safe work environment.

Mostrar más Leer menos
Institución
CGM-C
Grado
CGM-C









Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
CGM-C
Grado
CGM-C

Información del documento

Subido en
14 de septiembre de 2024
Número de páginas
5
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

CGM-C UPDATED Actual Exam Questions
and CORRECT Answers
The purpose of Construction Quality Management is to: - CORRECT ANSWER✔✔-
Achieve the quality established by properly developed requirements through the combined
responsibility, but separate, efforts of contractor and Government personnel


Construction Quality Management is the performance of tasks, which ensure that design and
construction is performed: - CORRECT ANSWER✔✔- According to plans and
specifications, on time, within a defined budget and a safe work environment.


Partnering relationships are based upon: - CORRECT ANSWER✔✔- Building trust and
dedication to common goals


It is the responsibility of Quality Assurance Personnel to: - CORRECT ANSWER✔✔-
Periodically verify that the contractors system of control is working effectively.


An effective contractor quality control (CQC) program will: - CORRECT ANSWER✔✔- Be
an incentive for work to be done correctly the first time resulting in earlier completion,
reduced field overhead costs, and greater profits.


The success or failure of all contractors is based upon: - CORRECT ANSWER✔✔- The
ability to control costs, finance work, estimate jobs, schedule the work, and maintain
effective quality control.


Quality Assurance Personnel have the responsibility to: - CORRECT ANSWER✔✔- Require
contractors to maintain the quality specified in the plans and specifications.


Inspection is: - CORRECT ANSWER✔✔- The process by which ongoing and completed
work is examined


During the punch-out inspection of a project: - CORRECT ANSWER✔✔- Quality
Assurance Personnel must assure that the contractor prepares a punch-list and makes
corrections.

, If there is disagreement whether the contractor's work complies with the contract: -
CORRECT ANSWER✔✔- The government makes the final determination


Characteristics that describe a definable feature of work (DFOW) include: - CORRECT
ANSWER✔✔- Cross-referenced listings to the contractors construction schedule that may
have more than one definable feature under a section of the specifications.


The _____________________ consists of daily checks of the work to assure continuing
compliance with contract requirements. - CORRECT ANSWER✔✔- Follow-up phase



The Quality Assurance Plan: - CORRECT ANSWER✔✔- Is a government management tool
establishing staffing, training, pre-award activities, and surveillance activities.


Testing is extremely important in Construction Quality Management and is performed by: -
CORRECT ANSWER✔✔- Both the contractor and the government


If the contractor does not provide an adequate superintendent, the contract allows the
contracting officer to: - CORRECT ANSWER✔✔- Require the contractor to assume
personal supervision of the work.


The Quality Control Plan: - CORRECT ANSWER✔✔- Is the foundation upon which quality
work is based and outlines planned quality control procedures.


Tests that are unannounced, randomly performed, and repeat quality control tests are: -
CORRECT ANSWER✔✔- Quality Assurance tests


If initial review of the Quality Control Plan shows it to be unacceptable: - CORRECT
ANSWER✔✔- The contractor makes changes before acceptance.



The contractor quality control organization: - CORRECT ANSWER✔✔- May vary in size
depending on the work being performed at a point in time.
$7.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
MGRADES Stanford University
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
1056
Miembro desde
1 año
Número de seguidores
102
Documentos
68976
Última venta
17 horas hace
MGRADES (Stanford Top Brains)

Welcome to MGRADES Exams, practices and Study materials Just think of me as the plug you will refer to your friends Me and my team will always make sure you get the best value from the exams markets. I offer the best study and exam materials for a wide range of courses and units. Make your study sessions more efficient and effective. Dive in and discover all you need to excel in your academic journey!

3.8

166 reseñas

5
72
4
30
3
42
2
8
1
14

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes