100% de satisfacción garantizada Inmediatamente disponible después del pago Tanto en línea como en PDF No estas atado a nada 4,6 TrustPilot
logo-home
Examen

CQM 6.4 Questions with Correct Answers 100% PassCQM 6.4 Question

Puntuación
-
Vendido
-
Páginas
2
Grado
A+
Subido en
01-08-2024
Escrito en
2024/2025

Importance of Testing -ANSWER - If tests are not performed properly, there are many construction procedures and materials that cannot be confirmed as adequate. Visual observation alone is insufficient. Types of Tests -ANSWER - The contractor performs quality control (QC) testing to determine whether construction procedures and materials are producing the desired contractual product. Procedures -ANSWER - The contractor must outline proposed "testing procedures" as defined in Section 01 45 00.00 10 and/or Section 01 45 00.00 20 in the QC Plan. These proposed procedures must be discussed at the Coordination Meeting or the Mutual Understanding Meeting. The contractor must provide a list of required control tests and specify whether the tests are to be performed by an independent, approved testing laboratory, or using their own personnel and facilities. Regardless of which method of testing the contractor uses, they are required to assure that specified laboratory procedures are used and that laboratory facilities are certified. QA tests -ANSWER - are unannounced sporadic tests that repeat QC tests. QA testing can be performed by: • Government personnel using the contractor's equipment and facilities, • An independent testing laboratory, or • A field office, district, or division government laboratory. Before testing begins, the following questions should be answered and verified against the approved QC Plan -ANSWER - • Has all required testing been identified? • Are test reporting requirements understood? • Have laboratory facilities and testing equipment been verified as acceptable? • Are laboratory personnel qualified? • Has the calibration of equipment been verified as accurate? • Is there a procedure for documenting corrective steps? After QC testing has begun, a thorough examination must be made of the test reports submitted to ascertain that: -ANSWER - • Reports are being submitted for all tests performed, • Reports are complete and accurate, and • Failing tests must be retested and cross r

Mostrar más Leer menos
Institución
CQM 6.4
Grado
CQM 6.4








Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
CQM 6.4
Grado
CQM 6.4

Información del documento

Subido en
1 de agosto de 2024
Número de páginas
2
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

CQM 6.4 Questions with Correct Answers 100% Pass
Importance of Testing -ANSWER - If tests are not performed properly, there are many construction procedures and materials that cannot be confirmed as adequate. Visual observation alone is insufficient.
Types of Tests -ANSWER - The contractor performs quality control (QC) testing to determine whether construction procedures and materials are producing the desired contractual product.
Procedures -ANSWER - The contractor must outline proposed "testing procedures" as defined in Section 01 45 00.00 10 and/or Section 01 45 00.00 20 in the QC Plan. These proposed procedures must be discussed at the Coordination Meeting or the Mutual Understanding Meeting.
The contractor must provide a list of required control tests and specify whether the tests are to be performed by an independent, approved testing laboratory, or using their own personnel and facilities.
Regardless of which method of testing the contractor uses, they are required to assure that specified laboratory procedures are used and that laboratory facilities are certified.
QA tests -ANSWER - are unannounced sporadic tests that repeat QC tests. QA testing can be performed by: • Government personnel using the contractor's equipment and facilities, • An independent testing laboratory, or • A field office, district, or division government laboratory.
Before testing begins, the following questions should be answered and verified against the approved QC Plan -ANSWER - • Has all required testing been identified? • Are test reporting requirements understood? • Have laboratory facilities and testing equipment been verified as acceptable? • Are laboratory personnel qualified? • Has the calibration of equipment been verified as accurate? • Is there a procedure for documenting corrective steps?
After QC testing has begun, a thorough examination must be made of the test reports submitted to ascertain that: -ANSWER - • Reports are being submitted for all tests performed, • Reports are complete and accurate, and • Failing tests must be retested and cross referenced to the original failing test.
$10.49
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor
Seller avatar
daltonvicky

Conoce al vendedor

Seller avatar
daltonvicky West Virginia university
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
8
Miembro desde
1 año
Número de seguidores
2
Documentos
446
Última venta
9 meses hace

0.0

0 reseñas

5
0
4
0
3
0
2
0
1
0

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes