ACI Field Grade 1 Practice Test | 50 Questions with 100% Correct Answers | Verified | Latest Update 2024 The temperature measuring device shall be cable of accurately measuring the temperature of freshly mixed concrete to 1°F throught a range of____________________________. - - 30 - 120°F It is acceptable to measure the temperature of freshly mixed concrete in the forms provided? - - The sensor of the temperature measuring device has at least 3 in. of cover in all directions. Composite samples are required even if the only purpose for obtaining the sample is to determine temperature. - - False The temperature measuring device is left in the freshly mixed concrete for at least _______________ but not more than 5 minutes. - - 2 minutes Test Method C1064/C1064M specifies a maximum temperature of freshly mixed concrete. - - False The elapsed time between obtaining the first and final portions of a composite sample shall not exceed ____________________. - - 15 minutes Individual samples shall be combined and remixed with a shovel the minimum amount necessary to ensure uniformity. - - True The following test must be started within 5 minutes after obtaining the final portion of the composite sample: - - Slump, Temperature, Air Content The concrete sample must be protected from? - - Contamination & Evaporation When strength specimens are to be made, the min

Mostrar más Leer menos
Institución
ACI FIELD 1
Grado
ACI FIELD 1









Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
ACI FIELD 1
Grado
ACI FIELD 1

Información del documento

Subido en
5 de julio de 2024
Número de páginas
6
Escrito en
2023/2024
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

ACI Field Grade 1 Practice Test | 50 Questions with 100%
Correct Answers | Verified | Latest Update 2024

The temperature measuring device shall be cable of accurately measuring the temperature of
freshly mixed concrete to 1°F throught a range of____________________________. - - 30 - 120°F



It is acceptable to measure the temperature of freshly mixed concrete in the forms provided? -
- The sensor of the temperature measuring device has at least 3 in. of cover in all directions.



Composite samples are required even if the only purpose for obtaining the sample is to determine
temperature. - - False



The temperature measuring device is left in the freshly mixed concrete for at least _______________
but not more than 5 minutes. - - 2 minutes



Test Method C1064/C1064M specifies a maximum temperature of freshly mixed concrete. - -
False



The elapsed time between obtaining the first and final portions of a composite sample shall not
exceed ____________________. - - 15 minutes



Individual samples shall be combined and remixed with a shovel the minimum amount necessary
to ensure uniformity. - - True



The following test must be started within 5 minutes after obtaining the final portion of the
composite sample: - - Slump, Temperature, Air Content



The concrete sample must be protected from? - - Contamination & Evaporation



When strength specimens are to be made, the minimum sample size is __________________. -
- 1.0 ft3

, Portions of the composite should be taken from the _______________of the batch discharge. -
- Middle



A composite sample taken from a paving mixer consists of _______________ individual samples
taken from different portions of the pile. - - Five



The process of removing aggregate larger than a designated size from the fresh concrete by sieving
it on a sieve of the designated size is know as? - - Wet Sieving



The slump test is considered applicable to plastic concrete having a coarse aggregate up to
____________________. - - 1 1/2 in.



The height of the slump mold is_________________. - - 12 inches



The interior surface of the slump mold shall be relatively smooth and free from projections. -
- True



The tamping rod used for the slump test shall have a minimum length of ____________ and a
maximum length of _______________. - - 16 in. & 24 in.



The slump mold is filled in ___________ layers of _______________. - - 3, equal volume



If the concrete subsides below the top of the slump mold while rodding the top layer, the test is
invalid. - - False



Slump is determined by measuring the vertical distance between? - - The top of the mold and
the original displaced center of the top surface of the specimen.



Slump is reported to the nearest? - - 1/4 in.
$14.39
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
MERCYTRISHIA Howard Community College
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
182
Miembro desde
1 año
Número de seguidores
35
Documentos
10800
Última venta
1 día hace
MercyTrishia

On this page, you find all documents, package deals offered by seller MercyTrishia

3.8

37 reseñas

5
16
4
7
3
10
2
0
1
4

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes