100% de satisfacción garantizada Inmediatamente disponible después del pago Tanto en línea como en PDF No estas atado a nada 4.2 TrustPilot
logo-home
Examen

API 653 COMPREHENSIVE QUESTIONS AND VERIFIED CORRECT ANSWER EXAM PREPERATION NEWEST UPDATE 2024

Puntuación
-
Vendido
-
Páginas
34
Grado
A+
Subido en
09-05-2024
Escrito en
2023/2024

API 653 COMPREHENSIVE QUESTIONS AND VERIFIED CORRECT ANSWER EXAM PREPERATION NEWEST UPDATE 2024

Institución
Grado











Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Grado

Información del documento

Subido en
9 de mayo de 2024
Número de páginas
34
Escrito en
2023/2024
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

API 653 COMPREHENSIVE QUESTIONS AND VERIFIED
CORRECT ANSWER\ EXAM PREPERATION
NEWEST UPDATE 2024

All repair and alteration work shall be approved at all designated hold points and
after completion:
A) Need not be approved if approved will delay work progress
B) By the repair organization of the repairs were done according to the specified
repair and/or alteration procedures
C) By the authorized inspector or experienced storage tank engineer
D) By the authorized inspector only
C
Alterations to storage tanks, which comply with API 650, must be authorized by:
A) The owner/user
B) The storage tank engineer
C) The authorized inspector
D) The repair organization
B

API 653 defines a "Storage tank engineer" as:
A) A registered professional engineer in structural steel fabrication
B) Person or organization who is knowledgeable and experienced in the
engineering disciplines associated with evaluating the integrity and reliability of
aboveground storage tanks
C) the engineering department of a contractor who makes repairs to aboveground
storage tanks
D) A professional engineer who is also an authorized API 653 inspector
B
Similar service is means of estimating corrosion rates that:
A) Is Seldom used as a means of scheduling internal inspection intervals
B) Ignores environmental factors in the determination of corrosion rates
C) May be used in addition to or in lieu of actual measurement of corrosion rates
D) Is generally considered as the best methodology for establishing the
inspection intervals
C
Controlled Deposition welding methods, in lieu of PWHT, is limited to:
A) P-1 materials
B) P-1 and P-3 Materials only
C) P-1, P3, and P4 materials only
D) P-5A materials
C
Inspection hold points, for tank reconstruction, shall be designated by:
A) The authorized inspector
B) An engineer experienced in storage tank design

,C) Agreement between tank owner/user and reconstruction contractor
D) Agreement between and engineer and the authorized
A

A record of non-essential variables used during welding of the test coupon is:
A) Optional on the PQR
B) Optional on the WPS
C) Required on the PQR
D) Required on the WPQ
A
Cracks is the shell to bottom weld:
A) Shall be evaluated per the "As built" Standard
B) Shall be removed
C) Shall be evaluated on a case by case basis
D) Shall be evaluated per API 579
B
What welding process is most widely used in the repair of process equipment?
A) GMAW
B) GTAW
C) SMAW
D) FCAW
C
The owner has decided to install a new bottom in an AST. The new bottom will be
installed through existing tombstone reinforcing plates. One Method is to remove
the lower portion of the reinforcing plate. After the new or replaced section is
installed, the splice weld shall:
A) Visually examined only
B) Magnetic particle examined only
C) Liquid penetrate examined only
D) Ultrasonic shear wave examined only
B
Which of the following is an advantage of thick film reinforced tank bottom
lining?
A) easier to apply than thin film
B) initial cost is typically less than thin film
C) Provides greater resistance to moisture ingress permeation
D) Generally more accurate MFL floor scans
C
The purpose of reviewing the welder performance qualification (WPQ) is to:
A) Verify that welder are qualified to perform the welding given its position and
process
B) Verify that welds made in compliance with the WPS meet requirements
C) Verify that the welding procedure specification can produce quality welds
D) Verify that welders are qualified to perform the welding, including all essential
and nonessential variables
A

,The recommended type of internal floating roof is the:
A) Double Deck
B) Annular pontoon
C) Pan type
D) Single steel deck
B
API Publication 2201 on hot tapping and in-service welding covers:
A) Welding requirements
B) technical aspects
C) Inspection requirements
D) Safety aspects
D
A repair is completed on a nozzle that was originally postweld heat
treated(PWHT). It has been determined that PWHT, of the repair, is inadvisable.
Who is required to conduct a metallurgical review prior to applying one of the
alternative methods permitted in API 653?
A) A professional engineer registered in one or more states or provinces of
Canada
B) A Storage tank engineer
C) The Authorized inspector responsible for the repair inspection
D) A Metallurgical engineer experienced in alternative PWHT
B
What is another term used for "Stray currents"?
A) Short circuits
B) Positive currents
C) Impressed Currents
D) Interface currents
D
Thick-film linings are commonly reinforced with which of the following?
A) Sand and small diameter gravel
B) Copper wire, Stainless steel wire, and low alloy steel mesh fabric
C)Chopped PVC piping, copped ABS Piping and resin beads
D) Woven glass mat, chopped glass fibers, and organic fibers
D
How and to what extent are new welds for tank bottom plates required to be
examined?
A) Newly welded bottom joints shall be tested their entire length using liquid
penetrate
B) Newly welded bottom joints shall be tested their entire length using a vacuum
box and a solution film, or a tracer gas and detector
C) Newly welded bottom joints shall be tested their entire length using visual
examination
D)Newly welded bottom joints shall be tested their entire length using wet
fluorescent magnetic particle examination
B

, According to API 653, no welding is permitted when the temperature of the base
metal is below what value?
A) Base metal temperature below -20 F
B) Base metal temperature below 0 F
C) Base metal temperature below 20 F
D) Base metal temperature below 30 F
B
IF an AST is fabricated of material of unknown toughness and meets the
thickness and temperature exemption curve of API 653, the storage tank engineer
must concur, in writing, with the alternative weld method in lieu of PWHT. Who is
required to authorize the alternative and how must this be accomplished?
A) The owner/operator in writing
B) The Owner/operator verbally
C) The Authorized Inspecor in writing
D) The Authorized Inspector verbally
A
When must an evaluation, to determine the suitability for continued use, be
conducted?
A) Evaluations shall be conducted when a tank inspection reveals a change has
occurred from the original physical condition of a tank.
B) Evaluations shall be conducted at least annually
C) Evaluations shall be conducted at an interval not to exceed the calculated tank
inspection frequency
D) Evaluations shall be conducted once each ten years of service
A
Inspection Hold points and minimum documentation to be submitted upon job
completion for repairs and alterations will be designated by the:
A) Owner/User's engineering department
B) Repair organization
C) authorized inspector
D) Storage tank inspector
C
In a SMAW electrode, the "1" refers to:
A) Electrode type
B) Coating characteristics
C) Chemical composition
D) Welding position
D
NDE is defined as those inspection methods which allow materials to be
examined:
A) without damaging the component
B) As an adjunct to visual examination
C) without changing or destroying their usefulness
D) Without using any mechanical force
C
$17.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
MEGAMINDS Chamberlain University College of Nursing
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
3896
Miembro desde
3 año
Número de seguidores
84
Documentos
2975
Última venta
1 semana hace
Top sellers

I specialize in crafting papers of various topics and complexities, always meeting deadlines with punctuality and precision. Whether it's research papers, case studies, or psychology papers, I'm committed to delivering engaging and informative content. With a passion for academic writing, I excel in structuring papers and presenting information creatively. Client satisfaction is my priority, and I take pride in impressing them with high-quality work. Your requirements are my focus, ensuring fresh ideas, consistent structure, and adherence to academic formatting rules. Additionally, for every referred student who completes and pays for an assignment transparently, I offer a complimentary assignment completion as a token of appreciation. Your satisfaction drives my dedication to excellence!

Lee mas Leer menos
4.4

712 reseñas

5
428
4
211
3
50
2
9
1
14

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes