100% de satisfacción garantizada Inmediatamente disponible después del pago Tanto en línea como en PDF No estas atado a nada 4,6 TrustPilot
logo-home
Examen

Redefine Your Study Habits with the [Project Management A Systems Approach to Planning, Scheduling, and Controlling,Kerzner,11e] 2024 Test Bank

Puntuación
-
Vendido
1
Páginas
66
Grado
A+
Subido en
09-08-2023
Escrito en
2023/2024

Embrace your pathway to academic success with the Test Bank for [Project Management A Systems Approach to Planning, Scheduling, and Controlling,Kerzner,11e]. This comprehensive tool is designed with one thing in mind - your exam success. It boasts of real practice exam questions, closely mimicking official exams to give you an edge in your preparation. Equipped with detailed answers, it serves as an effective learning resource. Turn the academic year of into your season of triumph, start preparing today.

Mostrar más Leer menos
Institución
Grado











Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Libro relacionado

Escuela, estudio y materia

Institución
Grado

Información del documento

Subido en
9 de agosto de 2023
Número de páginas
66
Escrito en
2023/2024
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

CHAPTER 1: OVERVIEW


(E) 1. In today’s market, which of the following industries appears to have a need for
project management?
A. Aerospace & defense
B. Construction
C. Information systems
* D. All industries have a need for project management


(M) 2. Which of the following is not one of the PMBOK  Guide’s five process
groups?
* A. Feasibility studies
B. Planning
C. Execution
D. Closure


(E) 3. Which of the following is normally not one of the traditional components of
the triple constraint?
A. Within time
B. Within cost
C. Within performance (Scope, technology or quality)
* D. Accepted by the customer


(M) 4. Which of the following is a potential benefit of using project management?
A. Maximization of continuous reporting
B. No need for identification of functional responsibilities
* C. Identification of time limits for scheduling
D. No need for a project management methodology


(E) 5. Which of the following functions of classical management is generally not
performed by the project manager?
A. Planning
B. Organizing
* C. Staffing
D. Controlling


(M) 6. Which of the following three types of deliverables discussed in the book would
be used to classify the final report that must be presented to the customer at the
end of the project?
A. Hardware deliverables

, * B. Software deliverables
C. Interim deliverables
D. Validation deliverables


(E) 7. Which of the following is not an organizational stakeholder?
A. Executive officers
B. Unions
C. Employees
* D. Customers


(E) 8. Which of the following is not a product/market stakeholder?
* A. Creditors
B. Customers
C. Suppliers
D. Governments


(E) 9. Which of the following is not a capital market stakeholder?
A. Banks
* B. Unions
C. Shareholders
D. Creditors


(M) 10. Which of the following is directly controlled by the project manager?
A. Money
B. Manpower
C. Information / technology
* D. None of the above


(H) 11. Which of the following is reflective of the changes in project management
according to Dr. Thamhain?
A. Moving from dynamic to linear processes
* B. Moving toward full utilization of information technology
C. Moving away from the use of an enterprise-wide methodology
D. Moving from effectiveness to efficiency


(E) 12. Successful project management requires a good daily working relationship
between project and line managers.
* A. True
B. False

,(E) 13. Successful project management does not require that people understand how to
report to multiple bosses.
A. True
* B. False


(E) 14. The project manager’s role as an integrator of activities does not include
integration of activities necessary to:
A. Develop the plan
B. Execute the plan
C. Make changes to the plan
* D. All of above are PM roles


(M) 15. The PM’s role with regard to interface management does not include
interfacing:
A. Within the project team
B. Between the project team and functional organizations
C. Between the project team and senior management
* D. Between senior management and various external stakeholders


(H) 16. Which of the following is the role of the PM rather than the role of the
functional manager?
* A. What work will be done
B. How the work will be done
C. Who will do it
D. Where it will be done


(E) 17. Which of the following problems affects the functional manager’s ability to
staff and support a project during execution?
A. Limited availability of resources
B. Predetermined deadlines
C. Unscheduled changes to the project plan
* D. all of the above


(H) 18. What type of project manager would have employees (i.e. team members) that
report directly to the project manager full-time for the duration of the project?
A. Lightweight team leader
B. Heavyweight team leader
* C. Tiger team leader
D. Leopard Team leader

, (H) 19. When team members take direction from both the project and line managers,
the type of project manager is usually
A. Lightweight team leader
* B. Heavyweight team leader
C. Tiger team leader
D. Leopard team leader


(H) 20. On a project headed up by a lightweight project manager, employees have their
performance reviews made by:
* A. Line managers only
B. Line managers with input from the project managers
C. Concurrence jointly by project managers and line managers
D. Project managers only


(H) 21. Which of the following is normally not part of a team member’s role?
A. Accepting responsibility for a deliverable
* B. Sharing information with the sponsor
C. Sharing information with the team
D. Completing the work at the earliest possible time.


(M) 22. In which life cycle phase do project sponsors become most actively involved in
the project?
* A. Initiation
B. Execution
C. Monitor and control
D. Closure


(M) 23. Which of the following is not part of the project sponsor’s role?
A. Conflict resolution
B. Priority-setting
* C. Selection of project team members
D. Monitoring performance at a high level


(M) 24. Project sponsorship almost always resides at the executive levels
A. True
* B. False


(M) 25. Which of the following promises can project managers make to functional
employees assigned to a project?
$38.49
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
PracticeExams my own
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
319
Miembro desde
2 año
Número de seguidores
194
Documentos
3266
Última venta
1 semana hace
ExamPrepZone

4.1

42 reseñas

5
26
4
4
3
7
2
2
1
3

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes