The A on a RACSI Matrix means _______.
Accountable – Person to whom the responsible person reports to and can approve R's
work
Asking – Person supports the project team by challenging proposed solutions
Answerable – Person is morally or legally responsible to a higher authority
Advising – Person gives advice to the team members
A _____ is most likely to have ‘A’ roles within a RASCI matrix for a textbook authoring
project.
publishing director
university professor
chapter author
project manager
_____ is designed to tell how much the total project should cost and when these costs will
occur.
Work breakdown structure
Project schedule
Milestone list
Budget
The I on a RACSI Matrix means _______.
Imaginative – Person brings creative skills into the project
Informed – Person that must be notified of results, but need not be consulted
Inspirer – Person is a leader who stimulates and excites people to action
Influencing – Person is shaping the project through work with stakeholders
,A _____ is most likely to have ‘C’ roles within a RASCI matrix for a textbook authoring
project.
project manager
chapter author
university professor
publishing director
A _____ is most likely to have ‘R’ roles within a RASCI matrix for a textbook authoring project.
university professor
chapter author
project manager
publishing director
The S on a RACSI Matrix means _______.
Support – Person provides resources of support to R, facilitates resolution of issues
Senior - Person is held in high regard as an advisor to the project team
Staffing – Person is responsible for project resourcing of permanent and temporary workers
Supervising – Person is the approver for all project work
RACI or RASCI charts are used by project managers to _______.
track requirements and traceability
to communicate project status
assign levels of responsibility to team members for work packages
determine the overall project budget
The R on a RACSI Matrix means _______.
, Responsible – Person that owns the activity and the work
Researching – Person acts as a researcher to assist the project team
Respected – Person is held in high regard as an advisor to the project team
Reinforcing – Person strengthens the project team with their skill sets
The C on a RACSI Matrix means _______.
Competent – Person is sufficiently qualified or efficient
Contributing – Person has sufficient experience to support the activity
Credible – Person that provides believable and accurate information
Consulted – Person with subject matter expertise or capability necessary to complete the
activity
, _____ is a document of all the work to be performed in order to complete the project.
Budget
Work breakdown structure
Milestone list
Project schedule
_____ is the basis for the detailed schedule and estimates.
RASCI Chart
Budget
Milestone list
Work breakdown structure
_____ is the listing of all of the work that must be performed to complete the project.
Milestone list
Budget
Accountable – Person to whom the responsible person reports to and can approve R's
work
Asking – Person supports the project team by challenging proposed solutions
Answerable – Person is morally or legally responsible to a higher authority
Advising – Person gives advice to the team members
A _____ is most likely to have ‘A’ roles within a RASCI matrix for a textbook authoring
project.
publishing director
university professor
chapter author
project manager
_____ is designed to tell how much the total project should cost and when these costs will
occur.
Work breakdown structure
Project schedule
Milestone list
Budget
The I on a RACSI Matrix means _______.
Imaginative – Person brings creative skills into the project
Informed – Person that must be notified of results, but need not be consulted
Inspirer – Person is a leader who stimulates and excites people to action
Influencing – Person is shaping the project through work with stakeholders
,A _____ is most likely to have ‘C’ roles within a RASCI matrix for a textbook authoring
project.
project manager
chapter author
university professor
publishing director
A _____ is most likely to have ‘R’ roles within a RASCI matrix for a textbook authoring project.
university professor
chapter author
project manager
publishing director
The S on a RACSI Matrix means _______.
Support – Person provides resources of support to R, facilitates resolution of issues
Senior - Person is held in high regard as an advisor to the project team
Staffing – Person is responsible for project resourcing of permanent and temporary workers
Supervising – Person is the approver for all project work
RACI or RASCI charts are used by project managers to _______.
track requirements and traceability
to communicate project status
assign levels of responsibility to team members for work packages
determine the overall project budget
The R on a RACSI Matrix means _______.
, Responsible – Person that owns the activity and the work
Researching – Person acts as a researcher to assist the project team
Respected – Person is held in high regard as an advisor to the project team
Reinforcing – Person strengthens the project team with their skill sets
The C on a RACSI Matrix means _______.
Competent – Person is sufficiently qualified or efficient
Contributing – Person has sufficient experience to support the activity
Credible – Person that provides believable and accurate information
Consulted – Person with subject matter expertise or capability necessary to complete the
activity
, _____ is a document of all the work to be performed in order to complete the project.
Budget
Work breakdown structure
Milestone list
Project schedule
_____ is the basis for the detailed schedule and estimates.
RASCI Chart
Budget
Milestone list
Work breakdown structure
_____ is the listing of all of the work that must be performed to complete the project.
Milestone list
Budget