100% de satisfacción garantizada Inmediatamente disponible después del pago Tanto en línea como en PDF No estas atado a nada 4.2 TrustPilot
logo-home
Examen

Project Management 2nd Edition by Pinto chapter 11

Puntuación
-
Vendido
1
Páginas
36
Subido en
27-10-2015
Escrito en
2014/2015

Project Management 2nd Edition by Pinto chapter 11 Test bank

Institución
Grado









Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
Estudio
Grado

Información del documento

Subido en
27 de octubre de 2015
Número de páginas
36
Escrito en
2014/2015
Tipo
Examen
Contiene
Preguntas y respuestas

Vista previa del contenido

Project Management, 2e (Pinto)
Chapter 11 Critical Chain Project Scheduling

11.1 True/False

1) Once the organization elevates its constraint, its system has no constraint.
Answer: FALSE
Diff: 2
Section: 11.1 The Theory of Constraints and Critical Chain Project Scheduling
Skill: Definition
AACSB Tag: Reflective

2) An organization's budget estimating process routinely misses the actual cost of a project by
25%. For the most recent project, the budget variance was a ridiculous 23%, but this must be
considered common cause variance.
Answer: TRUE
Diff: 2
Section: 11.1 The Theory of Constraints and Critical Chain Project Scheduling
Skill: Factual
AACSB Tag: Reflective

3) In order to estimate completion of a Gaussian distributed activity with a 90% or higher degree
of confidence, the time may be overestimated by as much as 200%.
Answer: TRUE
Diff: 2
Section: 11.2 CCPM and the Causes of Project Delay
Skill: Analytical
AACSB Tag: Reflective

4) If people believe that they built extra time into their initial estimates, they are usually more
likely to begin project work right away.
Answer: FALSE
Diff: 1
Section: 11.3 How Project Teams Waste the Extra Safety They Acquire
Skill: Conceptual
AACSB Tag: Reflective

5) Both positive and negative variation are usually passed downstream during a project.
Answer: FALSE
Diff: 2
Section: 11.3 How Project Teams Waste the Extra Safety They Acquire
Skill: Factual
AACSB Tag: Reflective




1
Copyright © 2010 Pearson Education, Inc.

, 6) The Central Limit Theorem states that if a number of probability distributions are summed,
the variance of the sum equals the sum of the variances of individual distributions.
Answer: TRUE
Diff: 2
Section: 11.4 The Critical Chain Solution to Project Scheduling
Skill: Analytical
AACSB Tag: Analytic Skills

7) A feeder buffer is a buffer that is created for a non-critical path activity.
Answer: TRUE
Diff: 1
Section: 11.4 The Critical Chain Solution to Project Scheduling
Skill: Definition
AACSB Tag: Reflective

8) An important element in critical chain scheduling is to change from a late-finish
(procrastination) approach to an early-start approach.
Answer: FALSE
Diff: 2
Section: 11.4 The Critical Chain Solution to Project Scheduling
Skill: Definition
AACSB Tag: Reflective

9) The critical chain is usually the same as the critical path.
Answer: FALSE
Diff: 2
Section: 11.4 The Critical Chain Solution to Project Scheduling
Skill: Factual
AACSB Tag: Reflective

10) The legal department is needed to review all contracts a project organization enters. The legal
department is continually swamped with work and all other departments find themselves waiting
on legal before they can begin their work. Legal is the drum for this organization.
Answer: TRUE
Diff: 2
Section: 11.6 Critical Chain Project Portfolio Management
Skill: Conceptual
AACSB Tag: Reflective

11.2 Fill in the Blank

1) Critical Chain Project Management is based on the __________.
Answer: Theory of Constraints
Diff: 1
Section: 11.1 The Theory of Constraints and Critical Chain Project Scheduling
Skill: Definition
AACSB Tag: Reflective

2
Copyright © 2010 Pearson Education, Inc.
$4.22
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada


Documento también disponible en un lote

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
smith2324 European Business School, London
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
94
Miembro desde
10 año
Número de seguidores
39
Documentos
196
Última venta
1 año hace

4.5

24 reseñas

5
13
4
9
3
2
2
0
1
0

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes