Certification Prep 2026/2027
Exam Questions and Answers |
Already Graded A+
What is a responsibility of the integrated product team during the risk
management process? - ANSWER ✔✔Develop and implement the
risk process planning outlined in key program documents and support
the program manager and the risk management board as required.
During EMD, what risks should be identified related to critical
manufacturing processes? - ANSWER ✔✔Manufacturing and supply
chain.
,During the MSA phase, what do proactive activities to prevent technical
risks focus on? - ANSWER ✔✔Developing requirements.
What is an appropriate action to monitor a moderate issue with staff
shortages on a program? - ANSWER ✔✔Update and review the
issue regularly and analyze potential changes to the issue level and
potential associated risks.
What is the appropriate corrective action for a major water leak that has
permanently damaged 45% of the servers? - ANSWER ✔✔Control.
Which stage of the issue management process is characterized by
testing a new system that drains battery after 5 hours? - ANSWER
✔✔Issue identification.
Is the interdependency of five separate R&D projects for a new vessel a
risk or an opportunity? - ANSWER ✔✔Risk.
Which risk monitoring tool is most appropriate for teams in different
locations needing access to risk data? - ANSWER ✔✔Risk
management information system.
What risk control approach is appropriate for developing a new diving
helmet with untested materials? - ANSWER ✔✔Design of
experiments.
,What type of risks can be identified from a Monte Carlo simulation? -
ANSWER ✔✔Cost and schedule.
What are the most common sources of risk in acquisition? -
ANSWER ✔✔Cost, schedule, and human systems integration.
What type of risk category describes changes to a prototype drone
system that increase cost and schedule? - ANSWER
✔✔Programmatic.
What is a good method for using risk identification tools? - ANSWER
✔✔Combine a top level method with a lower level method.
Where are the likelihood and consequence parameters documented? -
ANSWER ✔✔The Program Risk Process (PRP) document.
At what level of the organizational structure is approval to move a
program into the next acquisition phase made? - ANSWER
✔✔Executive level.
What is a good example of a framing assumption? - ANSWER
✔✔Contracts will offer mature designs that allow prototypes to be
delivered in five months.
COPYRIGHT©NINJANERD 2025/2026. YEAR PUBLISHED 2026. COMPANY REGISTRATION NUMBER: 619652435. TERMS OF USE. PRIVACY
STATEMENT. ALL RIGHTS RESERVED
3
, What is a critical success factor for effective risk management? -
ANSWER ✔✔Aligning government and contractor risk management.
Which step of the DOD risk management process involves developing,
implementing, and documenting the process? - ANSWER
✔✔Planning.
What is the top-down method of WBS construction used for? -
ANSWER ✔✔Procurement of products.
What are the last three steps of the bottom-up method in WBS
construction? - ANSWER ✔✔Review and discuss task categories,
ensure all tasks are listed correctly, finalize the WBS.
What is a control account in a WBS? - ANSWER ✔✔A natural
management point for planning that represents work assigned to one
responsible organizational element.
What is the difference between a Program WBS and a Contract WBS? -
ANSWER ✔✔A Program WBS includes both government and
contractor efforts, while a Contract WBS includes only contractor effort.
What type of common element is a technical publication? - ANSWER
✔✔Data.