C722- UNIT 5 -Project Management Questions and All Correct Answers 2026 Update.

Document preview thumbnail
Vista previa 2 fuera de 11 páginas

What does PERT stand for - Answer Project evaluation and review technique What does CPM stand for? - Answer Critical path method What does CCPM stand for? - Answer Critical chain project management What is The Waterfall method? - Answer a traditional practice which found its best use in software and hardware development. What does PRINCE2 stand for - Answer Projects in controlled environments ____________________Developed in the 1950s for the U.S. Navy, this method uses statistical analysis to estimate activity duration times PERT (Project evaluation and review technique) CPM (Critical path method) CCPM (Critical chain project management ) Waterfall Method PRINCE2 (Projects in controlled environments) - Answer PERT (Project evaluation and review technique) Correct! PERT was developed in the 1950s for the U.S. Navy. This method uses statistical analysis to estimate activity duration times. ______________Used previously in software development, this method organizes project tasks into linear workflows PERT (Project evaluation and review technique) CPM (Critical path method) CCPM (Critical chain project management )

Vista previa del contenido

C722- UNIT 5 -Project Management
Questions and All Correct Answers
2026 Update.


What does PERT stand for - Answer Project evaluation and review technique



What does CPM stand for? - Answer Critical path method



What does CCPM stand for? - Answer Critical chain project management



What is The Waterfall method? - Answer a traditional practice which found its best use in
software and hardware development.



What does PRINCE2 stand for - Answer Projects in controlled environments



____________________Developed in the 1950s for the U.S. Navy, this method uses statistical
analysis to estimate activity duration times



PERT (Project evaluation and review technique)

CPM (Critical path method)

CCPM (Critical chain project management )

Waterfall Method

PRINCE2 (Projects in controlled environments) - Answer PERT (Project evaluation and review
technique)



Correct! PERT was developed in the 1950s for the U.S. Navy. This method uses statistical
analysis to estimate activity duration times.



______________Used previously in software development, this method organizes project tasks
into linear workflows



PERT (Project evaluation and review technique)

CPM (Critical path method)

CCPM (Critical chain project management )

, Waterfall Method

PRINCE2 (Projects in controlled environments) - Answer Waterfall Method



Correct! Waterfall was used previously in software development. This method organizes project
tasks into linear workflows.



___________________Developed for the Dupont Corporation to estimate activity time
durations, this method assumes time can be reliably estimated.



PERT (Project evaluation and review technique)

CPM (Critical path method)

CCPM (Critical chain project management )

Waterfall Method

PRINCE2 (Projects in controlled environments) - Answer CPM (Critical path method)



Correct! CPM was developed for the Dupont Corporation to estimate activity time duration and
assumes time can be reliably estimated.



____________Focuses on managing the uncertainties of a project and builds buffers into the
schedule to prevent key activities from failing.



PERT (Project evaluation and review technique)

CPM (Critical path method)

CCPM (Critical chain project management )

Waterfall Method

PRINCE2 (Projects in controlled environments) - Answer CCPM (Critical chain project
management )



Correct! Critical chain focuses on managing the uncertainties of a project and builds buffers into
the schedule to prevent key activities from failing.



_____________Focuses on the specification of outputs, including very specific processes and
terminology



PERT (Project evaluation and review technique)

CPM (Critical path method)

CCPM (Critical chain project management )

Información del documento

Subido en
31 de julio de 2026
Número de páginas
11
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$12.49

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
TestSolver9
3.5
(165)
Vendido
958
Seguidores
128
Artículos
30723
Última venta
2 días hace


Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes