True or False: Plans are created to identify people who are not doing their jobs. - Answer False: To determine how to get the job done True or False: The project scope statement is all that is needed to complete all project planning. - Answer False: The scope statement is only one of several docs needed to generate planning. True or False: As long as we have a complete checklist, we can be assured that all planning for the project is complete. - Answer False A checklist may not include each and every task required. A checklist only states that the task has been addressed, not if it is successfully completed True or False: Once the project plan is written, it never changes. - Answer False Approved changes are possible at any time in the project life cycle and can cause plans to change. The project areas that require the project manager to plan extensively during the planning process are schedules, budget, quality, and ________ needed to complete the job. a. resources b. project charter c. issues - Answer a. resources The project manager needs to plan for the human and material resources that are required to get the job done. All planning documents are______. a. complex b. checklists c. living documents - Answer c. living documents

Vista previa del contenido

C722- Unit Module 18-WGU Project
Management Questions and All
Correct Answers.
True or False:

Plans are created to identify people who are not doing their jobs. - Answer False: To
determine how to get the job done



True or False:

The project scope statement is all that is needed to complete all project planning. - Answer
False: The scope statement is only one of several docs needed to generate planning.



True or False:

As long as we have a complete checklist, we can be assured that all planning for the project is
complete. - Answer False

A checklist may not include each and every task required. A checklist only states that the task
has been addressed, not if it is successfully completed



True or False:

Once the project plan is written, it never changes. - Answer False

Approved changes are possible at any time in the project life cycle and can cause plans to
change.



The project areas that require the project manager to plan extensively during the planning
process are schedules, budget, quality, and ________ needed to complete the job.

a. resources

b. project charter

c. issues - Answer a. resources

The project manager needs to plan for the human and material resources that are required to
get the job done.



All planning documents are______.

a. complex

b. checklists

c. living documents - Answer c. living documents

, All planning documents are considered to be "living documents" because they all need to be
periodically reviewed to ensure that the plans are still valid.



Project charters often include the project scope, objectives, and __________.

a. assumptions

b. personel

c. budget - Answer a. assumptions

Assumptions about the project are included in the project charter.



What is developed from the project scope and statement of work?



a. the project charter



b. Gantt chart



c. the Work Breakdown Structure - Answer c. the Work Breakdown Structure

Descriptions from the project scope and statement of work are how the Work Breakdown
Structure is developed.



The ________ defines the project's outcomes in terms of objectives, specific deliverables,
acceptance criteria, technical requirements, milestones, constraints, and assumptions.

a. Project scope

b. Project charter

c. Statement of work - Answer c. statement of work

The statement of work defines the project's outcomes in terms of objectives, specific
deliverables, acceptance criteria, technical requirements, milestones, constraints, and
assumptions.



The __________ describes how the project outcomes will be created.

a. project scope

b. product scope

c. project charter - Answer a. project scope

The project scope describes how the project outcomes will be created.



During which phase does scope verification occur?

Información del documento

Subido en
31 de julio de 2026
Número de páginas
9
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$11.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
TestSolver9
3.5
(165)
Vendido
958
Seguidores
128
Artículos
30723
Última venta
2 días hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes